Friday, December 26th, 2025

Dordikhola Hydropower Project begins power generation



LAMJUNG: The Dordikhola Hydropower Project in Lamjung district has begun test production from Sunday.

The project with the capacity of 27 megawatt commenced test production after completing the entire construction works, Project Chief Munna Shakya said.

According to Shakya, the test production will continue for four to five days adding that commercial production of the power will begin once the test production was successful.

Powerhouse of the project is located at Ramchowkbensi of Bensisahar Municipality-11.

Started to build in 2016, the project was estimated to generate power in two and a half years but got delayed due to India’s economic blockade on Nepal, flood in the powerhouse in the Marsyangdi river last year, lockdown imposed during the coronavirus period and several other technical issues.

The total cost of the project is estimated to be around Rs 4.64 billion though it was expected to complete with an investment of Rs 4.23 billion.

Non-Resident Nepalis Association (NRNA) has invested 35.7 percent, IME Group has 34.3 percent and 30 percent of the public for the project development.

Publish Date : 29 August 2022 07:29 AM

Gold, silver prices hit new record highs in domestic market

KATHMANDU: Gold and silver prices have been rising continuously in

Deuba urges govt to create conducive election environment

KATHMANDU: Nepali Congress (NC) President Sher Bahadur Deuba has urged

Prachanda calls on revolutionary forces to unite above differences

KATHMANDU: Coordinator of the Nepali Communist Party (NCP), Pushpa Kamal

Communications Minister Kharel to hold talks with top leaders of major parties today

KATHMANDU: Minister for Communications and Information Technology and government spokesperson

Motorcyclist dead in road accident in Chitwan

CHITWAN: A motorcyclist has died in a road accident in