Micro hydel project resumes operation after maintenance



MYAGDI: The Darkhola second micro hydropower project based in Dhaulagiri Rural Municipality-2, Lulang has come into operation after maintenance. The hydel project was closed after the flood occurred in July this year caused damages.

The project with 43-KW capacity was shut when the flood-fed Darkhola in Lulang swept away power house and canal. Lulang is geographically remote and has no access to electricity linked to central transmission line and road transport.

Chairperson of Users’ Committee Gyan Bahadur Paika shared that the project was repaired at the cost of Rs 2.2 million with the assistance of Gandaki Province government and Dhaulagiri Rural Municipality.

“Test production was done successfully on Sunday following maintenance”, he shared, adding power supply would be regular within a couple of days.

Publish Date : 14 February 2022 10:59 AM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Report of commission formed to implement SC orders related to the transport sector submitted

KATHMANDU: The inquiry commission formed to implement the orders and

Chinese Communist Party sends congratulatory letter to RSP, expresses confidence in stronger ties

KATHMANDU: The Chinese Communist Party (CPC) has sent an official

PR members of parliament to get certified on Thursday

KATHMANDU: The 110 members of parliament (MPs) elected through proportional