Eight years on, bridge construction sees only 20 percent progress



DOTI: Eight years into construction, a bridge over the Seti River in Shikhar Municipality-10 in Doti district has witnessed only 20 percent physical progress.

The Federal Road Supervision and Monitoring Office, Road Division Office, Kulpate had signed a contract with the Pushpa-Rajendra JV Construction Company in 2014 to complete the construction works by the end of 2017.

Negligence on the part of the contractor has been blamed for the delay. The agreement has been extended four times in between. The 320-meter long bridge linking the KI Singh Highway costs Rs 262 million, including value-added tax. So far, Rs 32 million has been released for the project, said the Road Division Office.

The contractor has cited COVID-19 and lack of workforce for the delay, said engineer Yogendra Bahadur Adhikari, also an information officer of the Road Division Office.

Problems in the project foundation have caused the delay, said the contractor.

Publish Date : 12 February 2022 21:06 PM

Family seeks justice after student suffers alleged trauma at Budhanilkantha School

KATHMANDU: A family in Kathmandu has alleged that their daughter

National Assembly meeting scheduled for today; Finance Minister to table Appropriation Bill

KATHMANDU: A meeting of the National Assembly, the upper house

Wild elephants damage six houses in Udayapur

GAIGHAT: A herd of wild elephants has entered the Kumang

Revisiting Last Week: Consolidation and Confrontation

KAHTMANDU: Last week may eventually be remembered as the period

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of