Eight years on, bridge construction sees only 20 percent progress



DOTI: Eight years into construction, a bridge over the Seti River in Shikhar Municipality-10 in Doti district has witnessed only 20 percent physical progress.

The Federal Road Supervision and Monitoring Office, Road Division Office, Kulpate had signed a contract with the Pushpa-Rajendra JV Construction Company in 2014 to complete the construction works by the end of 2017.

Negligence on the part of the contractor has been blamed for the delay. The agreement has been extended four times in between. The 320-meter long bridge linking the KI Singh Highway costs Rs 262 million, including value-added tax. So far, Rs 32 million has been released for the project, said the Road Division Office.

The contractor has cited COVID-19 and lack of workforce for the delay, said engineer Yogendra Bahadur Adhikari, also an information officer of the Road Division Office.

Problems in the project foundation have caused the delay, said the contractor.

Publish Date : 12 February 2022 21:06 PM

Sunsari clash: Army deployed as tensions escalate

KATHMANDU: Security has been stepped up in Sunsari after a

Illegal egg harvesting allegations put Nepal’s IVF sector under scrutiny

KATHMANDU: Nepal’s growing in-vitro fertilisation (IVF) sector has come under

Minister Lamsal vows to address concerns of Nagdhunga tunnel-affected locals

KATHMANDU: Minister for Physical Infrastructure and Transport Sunil Lamsal has

Minister Mehta calls for social harmony after Sunsari clash

KATHMANDU: Minister for Health and Food Safety Nisha Mehta has

Two women found dead at same location in Nawalparasi

NAWALPARASI: Two women who were found unconscious near Aklamai Temple