Finance Ministry records problems facing national pride projects



KATHMANDU: The Finance Ministry has viewed that random planning of projects- avoiding actual need- was one of the significant reasons behind low development spending. Lack of clear legal provisions on selection and implementation of project warrants equal attention, according to the Ministry.

Currently, there are 25 national pride projects. Among them, only Upper Tamakoshi Hydropower Project has been completed. Similarly, construction of the Gautam Buddha International Airport at Bhairahawa has been finalized. Another International Airport at Pokhara has made progress.

However, the remaining projects have shown no noticeable progress. The Finance Ministry has further argued that preparatory works also lacked for the implementation of the project.

Other problems in the project implementation as the Ministry recorded are no clear standard for coordination among local and province levels, inadequate discussion with local people on benefits of the projects and its contribution to socio-economic transformation, initiation of procurement process without finalizing basics as project modality and estimation of time, sheer lack of coordination among government agencies, and human resources crunch, among others.

Publish Date : 12 February 2022 07:12 AM

EC proposes strict campaign rules, caps flag use at 10

KATHMANDU: The Election Commission (EC) has proposed new restrictions aimed

CPN-UML general convention: Voting taking place today

KATHMANDU: Voting at the 11th general convention of the CPN-UML

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Ministry of Labour to launch ‘Help to Help 10 Cell’

KATHMANDU: The Ministry of Labour, Employment and Social Security is

Four-lane Madi bridge in Tanahun nears completion

TANAHUN: Work on the four-lane bridge under construction in Damauli