Thursday, November 21st, 2024

This is why MCC transmission line seems crucial


10 February 2022  

Time taken to read : 6 Minute


  • A
  • A
  • A

KATHMANDU: Power production in Nepal is gradually increasing. So far, projects generating 2,900 megawatts of electricity have been connected to the Nepal Electricity Authority (NEA)’s system.

Three projects with a capacity of 3,500 megawatts are being developed while projects of 9,000 megawatts capacity are in the pipeline. Despite good progress in power production, challenges remain for transporting it from one place to another due to the lack of a transmission system.

According to NEA Executive Director Kulman Ghising, the construction of transmission lines and their towers has become like a project. The construction of transmission lines has become a ‘Herculean task’ due to numerous complexities and hurdles.

Moreover, the growing urbanization in the Kathmandu Valley has led to rising demand for electricity every year.

But the existing transmission system in place has not been able to cope with the demand, suggesting a dire need for an alternative transmission system.

Bearing this fact in mind, the government, some time ago, introduced a project to construct a 400-KV transmission line from Nanglebhare of Kathmandu to Ratmate of Nuwakot. The project is to be implemented as per the NEA’s master plan. The transmission will spread to Nawalparasi via Tanahu and towards Hetauda as well.

The total 312 kilometers long transmission system that is considered to be the backbone for the Kathmandu Valley, will link major cities like Pokhara, Hetauda, Narayangadh and Butwal. Three substations will be constructed at Lapsiphedi, Ratamata and Damauli with USD 400 million grant to be provided under the Millennium Challenge Corporation (MCC).

The substation at Ratamata in Nuwakot district will connect to the proposed 400 KV Rasuwagadhi-Kerung transmission line. Similarly, the proposed 400 KV Butwal-Gorakhpur transmission line will link with the 22 kilometers inter-country transmission line of Nepal and India.

MCC Nepal Compact is essential in constructing transmission lines to transport electricity within the country and export it to neighboring India, said Prakash Dulal, member of the Central Executive Committee of the Independent Power Producers’ Association, Nepal (IPPAN).

Risk of investment going to the drain

The electricity generated from projects in the Tamakosi and Bhotekosi corridors would be connected through this transmission line. Similarly, the power from most of the hydroelectricity projects, which are under construction or are preparing for construction in the river corridors of Rasuwa and Nuwakot, would be connected to this grid.

Energy entrepreneur Gyanendra Lal Pradhan said this transmission line is more significant also because the projects with more than 3,000 megawatts capacity, which are under construction at present, are being constructed in locations around it. Pradhan said the transmission line should be constructed without any confusion since the investment of the government and the private sector would go to ruins, the banks and financial institutions will also be economically bankrupt and the country itself will plunge into economic crisis in its absence.

The private sector has put in investment worth around Rs 60 billion in projects around this transmission line alone.

Pradhan emphasized that this transmission line is necessary also for transmitting electricity generated from the under-construction and ready for construction projects to the urban areas with high electricity demand and for exporting power to India and Bangladesh as well.

Similarly, the electricity to be generated from projects being built in the Budhigandaki and Kaligandaki corridors is to be connected to the same transmission line.

The US assistance project, Millennium Challenge Corporation, is investing in this transmission line considered important in terms of carrying electricity from the production sites to places where there is demand for it. This transmission line will be of assistance in transmitting surplus power produced in the country to the market in India and Bangladesh as well since it is also to be connected to the proposed Nepal-India second inter-country transmission line.

Nepal and India have reached a memorandum of understanding for the construction of the 400-KV capacity New Butwal Gorakhpur Trans-border Transmission Line with equal investment.

As per the government data, although there is the feasibility of producing around 83 thousand megawatts power in Nepal, only two percent of this or 2,100 megawatts power is being produced in the country at present.

Projects with a capacity of generating 610 megawatts are under construction from the government sectors while projects with the capacity of producing 3,506 megawatts power are under construction from the private sector at present.

Likewise, the power purchase agreement (PPA) has been concluded for projects with a capacity of 2,141 megawatts from the private sector and these projects are under construction phase. Power installation agreement has been concluded for projects producing a combined of 1,852 megawatts power and they are waiting for PPA, it is said.

(Ramesh Lamsal/RSS)

Publish Date : 10 February 2022 08:37 AM

India warns of ‘further damage’ to Canada ties

NEW DELHI: India warned Canada of “further damage” to already

Prime Minister Oli’s visit to China expected to further strengthen bilateral ties

KATHMANDU: A bilateral meeting was held between the leaders of

Cooperative fraud case: Former DIG Chhabilal Joshi’s statement begins in Kathmandu

KATHMANDU: The statement of Chhabilal Joshi, the then vice-chair of

Nepal-India military collaboration talks concluded at NA headquarters

KATHMANDU: Chief of the Army Staff Ashok Raj Sigdel and

Agriculture Ministry gathering details of loss and damage

KATHMANDU: The Ministry of Agriculture and Livestock has initiated data