Hydro project sees delay in equipment installation and production



KATHMANDU: The under-construction Rasuwagadhi hydropower project has witnessed a delay in the installation of equipment due to sheer ignorance on part of the contractor company.

No equipment has been so far installed in the powerhouse due to dillydallying of VOITH India, an Indian Company responsible for equipment placement.

Hydropower Project Chief Chhabi Gaire shared that they have repeatedly following up with the Indian company to comply with the memorandum of understanding.

The company was entrusted with the responsibility to accomplish the given works, including import and installation of equipment at the contracted amount of Rs 2.8 billion.

The 111-MW project requires a year-long time for installing the equipment in the powerhouse and so far 50 percent of the progress has to be made. However, it has resulted in a delay in the production of power from the project due to the negligence of the contractor.

The equipment to be installed in the powerhouse has been already stored on the project site and the installation would take momentum once the technical human resources are available. RSS

Publish Date : 30 September 2021 11:01 AM

NRB announces foreign currency exchange rates for Wednesday

KATHMANDU: Nepal Rastra Bank (NRB) has published the foreign exchange

Mbappe scores twice as France cruise into World Cup last 16

EAST RUTHERFORD: Kylian Mbappe scored twice as France defeated Sweden

World Cup: Norway beat Ivory Coast to reach last 16

TEXAS: Norway edged past Ivory Coast 2-1 in a tightly

Nepal Oil Corporation cuts fuel and LPG prices

KATHMANDU; Nepal Oil Corporation (NOC) has reduced the prices of

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of