Hydro project sees delay in equipment installation and production



KATHMANDU: The under-construction Rasuwagadhi hydropower project has witnessed a delay in the installation of equipment due to sheer ignorance on part of the contractor company.

No equipment has been so far installed in the powerhouse due to dillydallying of VOITH India, an Indian Company responsible for equipment placement.

Hydropower Project Chief Chhabi Gaire shared that they have repeatedly following up with the Indian company to comply with the memorandum of understanding.

The company was entrusted with the responsibility to accomplish the given works, including import and installation of equipment at the contracted amount of Rs 2.8 billion.

The 111-MW project requires a year-long time for installing the equipment in the powerhouse and so far 50 percent of the progress has to be made. However, it has resulted in a delay in the production of power from the project due to the negligence of the contractor.

The equipment to be installed in the powerhouse has been already stored on the project site and the installation would take momentum once the technical human resources are available. RSS

Publish Date : 30 September 2021 11:01 AM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

NC urges NA Chair to summon National Assembly session

KATHMANDU: The Nepali Congress (NC) has demanded that the session

Govt working hard to conduct March 5 election successfully: PM Karki

KATHMANDU: Prime Minister Sushila Karki has said the government has

Curfew imposed in Kamalamai municipality, Sindhuli

SINDHULI: The District Administration Office of Sindhuli has imposed a

Balen leaves Kumar Ben’s house after 10 hours

LALITPUR: Kathmandu Metropolitan City Mayor Balendra Shah left Lalitpur after