Hydro project sees delay in equipment installation and production



KATHMANDU: The under-construction Rasuwagadhi hydropower project has witnessed a delay in the installation of equipment due to sheer ignorance on part of the contractor company.

No equipment has been so far installed in the powerhouse due to dillydallying of VOITH India, an Indian Company responsible for equipment placement.

Hydropower Project Chief Chhabi Gaire shared that they have repeatedly following up with the Indian company to comply with the memorandum of understanding.

The company was entrusted with the responsibility to accomplish the given works, including import and installation of equipment at the contracted amount of Rs 2.8 billion.

The 111-MW project requires a year-long time for installing the equipment in the powerhouse and so far 50 percent of the progress has to be made. However, it has resulted in a delay in the production of power from the project due to the negligence of the contractor.

The equipment to be installed in the powerhouse has been already stored on the project site and the installation would take momentum once the technical human resources are available. RSS

Publish Date : 30 September 2021 11:01 AM

Nepal’s public debt nears Rs 2.8 trillion

KATHMANDU: Nepal’s public debt has nearly reached Rs 2.8 trillion,

Miraj Dhungana–led Gen-Z group continues protests today

KATHMANDU: The Gen-Z movement led by Miraj Dhungana is continuing

Nepal drawn in Group B for ICC Women’s T20 World Cup 2026 Global Qualifier

KATHMANDU: The match schedule for the ICC Women’s T20 World

Temporary hall being prepared for National Assembly winter session after fire damage

KATHMANDU: With the construction of the new Parliament building inside

Hetauda road expansion victims stage musical protest at Maitighar

KATHMANDU: Victims of the Hetauda road expansion project staged a