Hydro project sees delay in equipment installation and production



KATHMANDU: The under-construction Rasuwagadhi hydropower project has witnessed a delay in the installation of equipment due to sheer ignorance on part of the contractor company.

No equipment has been so far installed in the powerhouse due to dillydallying of VOITH India, an Indian Company responsible for equipment placement.

Hydropower Project Chief Chhabi Gaire shared that they have repeatedly following up with the Indian company to comply with the memorandum of understanding.

The company was entrusted with the responsibility to accomplish the given works, including import and installation of equipment at the contracted amount of Rs 2.8 billion.

The 111-MW project requires a year-long time for installing the equipment in the powerhouse and so far 50 percent of the progress has to be made. However, it has resulted in a delay in the production of power from the project due to the negligence of the contractor.

The equipment to be installed in the powerhouse has been already stored on the project site and the installation would take momentum once the technical human resources are available. RSS

Publish Date : 30 September 2021 11:01 AM

Elderly woman dies after falling from cliff

BAITADI: An elderly woman died after falling off a cliff

Silver price hits record high, crosses Rs 4,000 per tola

KATHMANDU: The price of silver reached a new record high

Senior leaders face difficulties in electronic voting at UML 11th General Convention

KATHMANDU: Senior leaders and elderly delegates have faced difficulties during

Finance Ministry tells provinces, local levels not to levy fees on goods transportation

KATHMANDU: The Ministry of Finance has told provincial and local

UML General Convention: Voting to elect new leadership begins

KATHMANDU: Voting at the 11th general convention of the CPN-UML