Hydro project sees delay in equipment installation and production



KATHMANDU: The under-construction Rasuwagadhi hydropower project has witnessed a delay in the installation of equipment due to sheer ignorance on part of the contractor company.

No equipment has been so far installed in the powerhouse due to dillydallying of VOITH India, an Indian Company responsible for equipment placement.

Hydropower Project Chief Chhabi Gaire shared that they have repeatedly following up with the Indian company to comply with the memorandum of understanding.

The company was entrusted with the responsibility to accomplish the given works, including import and installation of equipment at the contracted amount of Rs 2.8 billion.

The 111-MW project requires a year-long time for installing the equipment in the powerhouse and so far 50 percent of the progress has to be made. However, it has resulted in a delay in the production of power from the project due to the negligence of the contractor.

The equipment to be installed in the powerhouse has been already stored on the project site and the installation would take momentum once the technical human resources are available. RSS

Publish Date : 30 September 2021 11:01 AM

NA members draw govt attention to multiple issues

KATHMANDU: Members of the National Assembly have drawn the government’s

Govt forms five-member committee to assess land status in Phewa Lake’s boundaries 

KATHMANDU: The government has formed a five-member committee to determine

Heavy snowfall blankets Mustang, disrupts Muktinath pilgrimage

MUSTANG: Heavy snowfall has been reported in lower Mustang, including

Structure on land leased by Home Minister Gurung near Phewa Lake found unused

KATHMANDU: A piece of land reportedly leased by Home Minister

Govt serious about repatriating Nepalis affected by West Asia conflict: Foreign Minister

KATHMANDU: Foreign Minister Shishir Khanal has said the government is