Upper Tamakoshi to carry out test production from today



KATHMANDU: The Upper Tamakoshi Hydroelectric Project is set to carry out a test production starting today.

The Nepal Electricity Authority (NEA) said the test production will be carried out from June 27 to July 3.

The NEA said that it will also include managing the transmission line to connect the electricity to the national grid.

The 132 KV Khimti-Lamosanghu corridor will, meanwhile, remain closed during the period, according to the NEA.

Project chief Bigyan Shrestha informed that they will conduct the testing of the first unit of the plant from June 27 after the successful testing of an eight-kilometer-long tunnel.

Publish Date : 27 June 2021 11:45 AM

RSP Chair Rabi leaves for three-day India visit

KATHMANDU: Rastriya Swatantra Party (RSP) Chairman Rabi Lamichhane has left

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of

Artificial dam in community forest improves irrigation access in Dang

DANG: The construction of an artificial dam in the Rani

FRLD approves $20 million grant for Nepal’s flood recovery

KATHMANDU: The Fund for Responding to Loss and Damage (FRLD)

Tourist activity picks up in Myagdi following repairs to Beni–Jomsom road

MYAGDI: Tourist activity has begun to pick up at various