Power generation from Lower Modi hydel project suspended for three weeks



PARBAT: The Lower Modi-1 Hydropower Project in Parbat district that was damaged by flood on September 2 is yet to begin power generation.

The project officials said that immediate resumption of the power generation from the project is unlikely as the damage from the flood is quite huge in scale. Project’s canal, dam, share wall, slab and other structures have witnessed damages after the flood.

However, powerhouse of the project is unaffected from the flood but it could take more time to supply water from the canal.
Likewise, a tower of the transmission line of 132 KV capacity linking the powerhouse to Modi substation is collapsed in the disaster, making the power resumption more tough. The project said that around Rs 15 million is likely to cost for the development of a tower.

United Modi Hydropower Company’s Managing Director Upendra Gautam said that the company has suffered daily loss of Rs 1 million after the suspension in power generation while adding that total damage was evaluated Rs 50 million plus.

Publish Date : 24 September 2021 10:33 AM

PM Balen Shah calls emergency Cabinet meeting

KATHMANDU: Prime Minister (PM) Balendra Shah has called an emergency

Home Ministry to establish central command system to strengthen security

KATHMANDU: The Ministry of Home Affairs has decided to establish

Pokhrel questions transparency of foreign loans taken by Balen-led government

KATHMANDU: General Secretary of the CPN-UML Shankar Pokhrel has raised

Govt recalls 6 politically appointed ambassadors 

KATHMANDU: The government has decided to recall six ambassadors appointed

No quick fix for BP Highway as damage keeps route closed

KATHMANDU: The BP Highway, a vital lifeline connecting eastern Nepal