Sailung Construction vows to complete Nagarkot road expansion by coming March-end



BHAKTAPUR: The Kamalbinayak Nagarkot Road Construction Project and Sailung Construction Pvt Ltd have pledged to complete the construction of the much-awaited Bhaktapur-Nagarkot road by mid-March next year.

At an interaction program organized by Changunarayan municipality on Wednesday to mount pressure for an expedition of road construction, project chief Gautam Shrestha vowed to complete the works by mid-March.

It may be noted that the timeline for the construction and expansion of the Bhaktapur-Nagarkot road section has been extended for the seventh time.

On the occasion, Madhav Khadka of Sailung Construction admitted serious managerial errors on part of the contractor company in the road construction and pledged to complete the stipulated works soon.

Publish Date : 23 December 2021 15:00 PM

Radisson gas cylinder row: Department official contradicts Ministry’s claim

KATHMANDU: The Department of Industry, Commerce and Supplies under the

U.S. strategic oil reserve falls below 300 million barrels to 43-year low

WASHINGTON: The U.S. Strategic Petroleum Reserve has fallen below 300

Foreign Ministry’s 2026 Summer Fellowship and Internship programme concludes

KATHMANDU: The Institute of Foreign Affairs (IFA) has organised the

World Association of Press Councils calls for immediate release of Kishor Shrestha

KATHMANDU: The World Association of Press Councils (WAPC) has strongly

Journalist Kishor Shrestha remanded in custody for 3 days

KATHMANDU: The Kathmandu District Court has granted police permission to