Sailung Construction vows to complete Nagarkot road expansion by coming March-end



BHAKTAPUR: The Kamalbinayak Nagarkot Road Construction Project and Sailung Construction Pvt Ltd have pledged to complete the construction of the much-awaited Bhaktapur-Nagarkot road by mid-March next year.

At an interaction program organized by Changunarayan municipality on Wednesday to mount pressure for an expedition of road construction, project chief Gautam Shrestha vowed to complete the works by mid-March.

It may be noted that the timeline for the construction and expansion of the Bhaktapur-Nagarkot road section has been extended for the seventh time.

On the occasion, Madhav Khadka of Sailung Construction admitted serious managerial errors on part of the contractor company in the road construction and pledged to complete the stipulated works soon.

Publish Date : 23 December 2021 15:00 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Special convention factions stand firm: No consensus until Deuba steps down

KATHMANDU: The closed session of the Nepali Congress’ second special

US revokes over 100,000 visas, including thousands of student and specialized visas

WASHINGTON: The US Department of State has revoked more than

Electronic cigarettes worth Rs 22.4 million seized at Korala border

KATHMANDU: Electronic cigarettes (vapes) worth Rs 22.4 million were seized

Nepali Congress executive committee meeting postponed, rescheduled for tomorrow at 8 a.m.

KATHMANDU: The Nepali Congress Central Executive Committee meeting, which began