Sailung Construction vows to complete Nagarkot road expansion by coming March-end



BHAKTAPUR: The Kamalbinayak Nagarkot Road Construction Project and Sailung Construction Pvt Ltd have pledged to complete the construction of the much-awaited Bhaktapur-Nagarkot road by mid-March next year.

At an interaction program organized by Changunarayan municipality on Wednesday to mount pressure for an expedition of road construction, project chief Gautam Shrestha vowed to complete the works by mid-March.

It may be noted that the timeline for the construction and expansion of the Bhaktapur-Nagarkot road section has been extended for the seventh time.

On the occasion, Madhav Khadka of Sailung Construction admitted serious managerial errors on part of the contractor company in the road construction and pledged to complete the stipulated works soon.

Publish Date : 23 December 2021 15:00 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Nearly Rs 12 billion deposited to PM Natural Disaster Relief Fund

KATHMANDU: Nearly Rs 12 billion has been collected in the

Bhotekoshi flood: 13,396 people rescued so far

KATHMANDU: A total of 13,396 people have been rescued so

Commitment to fulfill Gen-Z martyrs’ dream with zero tolerance to corruption

KATHMANDU: Acting Mayor of Kathmandu Metropolitan City, Sunita Dangol, has

Bhotekoshi flood leaves Gatlang cabbage farmers increasingly worried

RASUWA: Cabbage farmers in Gatlang have grown increasingly concerned after