Insufficient budget mars upgradation of Karnali Highway



KHALANGA: The upgradation job of Nagma-Gamgadhi road section of Karnali Highway has been affected for lack of sufficient budget to advance the construction task.

The task was affected as Rs 97 million budget released by the federal government for the current fiscal year was completed in the first three months. With the completion of the budget, the federal government again sent Rs 50 million but that amount too has finished.

Chief of Road Division Office, Jumla, Leela Bhandari said that the construction work is not taking place as per the estimate. The job of gravel and drain construction are incomplete and payment of Rs 120 million for the contractor is delayed due to insufficient budget.

In the current fiscal year, gravel work of 34 kms road along the Gamgadhi-Nagma is completed and the gravel work of 59 kms is yet to carry out.

Publish Date : 23 February 2021 12:40 PM

Magnetic cards, special lenses used to cheat gamblers at Casino Waldo in Thamel

KATHMANDU: Kathmandu police have uncovered a sophisticated gambling fraud at

Nepali Congress holds central executive meeting amid possible convention delay

KATHMANDU: The Nepali Congress is holding a meeting of its

Political dialogue with parties positive and productive: Law Minister Sinha

KATHMANDU: Minister for Law, Justice and Parliamentary Affairs Anil Kumar

NEPSE inches up by 1.37 points, turnover declines

KATHMANDU: The Nepal Stock Exchange (NEPSE) index edged up by

Will Nepal’s polls be held as planned?

KATHMANDU: With just 71 days remaining for the House of