Insufficient budget mars upgradation of Karnali Highway



KHALANGA: The upgradation job of Nagma-Gamgadhi road section of Karnali Highway has been affected for lack of sufficient budget to advance the construction task.

The task was affected as Rs 97 million budget released by the federal government for the current fiscal year was completed in the first three months. With the completion of the budget, the federal government again sent Rs 50 million but that amount too has finished.

Chief of Road Division Office, Jumla, Leela Bhandari said that the construction work is not taking place as per the estimate. The job of gravel and drain construction are incomplete and payment of Rs 120 million for the contractor is delayed due to insufficient budget.

In the current fiscal year, gravel work of 34 kms road along the Gamgadhi-Nagma is completed and the gravel work of 59 kms is yet to carry out.

Publish Date : 23 February 2021 12:40 PM

Lumbini’s policies and programmes prioritize agriculture, tourism, and employment

SIDDHARTHANAGAR: The Lumbini Province government has presented its annual policies

Joint Secretary Dangol appointed Director General of Civil Aviation Authority

KATHMANDU: The government has appointed Joint Secretary Mukesh Dangol as

President to address Republic Day ceremony at PM Shah’s request

KATHMANDU: President Ram Chandra Paudel is set to address the

Pokhara Metropolitan continues drive to remove encroachments along Firke Khola

POKHARA: The Pokhara Metropolitan City has continued its campaign to

Govt faces challenge of raising civil servant salaries ahead of new budget

KATHMANDU: With only four days remaining before the government unveils