Insufficient budget mars upgradation of Karnali Highway



KHALANGA: The upgradation job of Nagma-Gamgadhi road section of Karnali Highway has been affected for lack of sufficient budget to advance the construction task.

The task was affected as Rs 97 million budget released by the federal government for the current fiscal year was completed in the first three months. With the completion of the budget, the federal government again sent Rs 50 million but that amount too has finished.

Chief of Road Division Office, Jumla, Leela Bhandari said that the construction work is not taking place as per the estimate. The job of gravel and drain construction are incomplete and payment of Rs 120 million for the contractor is delayed due to insufficient budget.

In the current fiscal year, gravel work of 34 kms road along the Gamgadhi-Nagma is completed and the gravel work of 59 kms is yet to carry out.

Publish Date : 23 February 2021 12:40 PM

Elderly woman dies after falling from cliff

BAITADI: An elderly woman died after falling off a cliff

Silver price hits record high, crosses Rs 4,000 per tola

KATHMANDU: The price of silver reached a new record high

Senior leaders face difficulties in electronic voting at UML 11th General Convention

KATHMANDU: Senior leaders and elderly delegates have faced difficulties during

Finance Ministry tells provinces, local levels not to levy fees on goods transportation

KATHMANDU: The Ministry of Finance has told provincial and local

UML General Convention: Voting to elect new leadership begins

KATHMANDU: Voting at the 11th general convention of the CPN-UML