Construction of 12 RCC bridges along Karnali highway completed



SURKHET: Construction of 12 RCC bridges along the Karnali highway (Surkhet-Jumla road section) has been completed in the last fiscal year 2020/21.

According to the Road Division Office, Surkhet, the construction of these bridges started in 2016/17 completed in the last fiscal year. Passengers have faced a lot of hardships for a long in the lack of RCC bridges at most of the places of Karnali highway.

Engineer at Road Division Office, Surkhet, under the Federal Road Supervision and Monitoring Office, Tularam Sharma, said that the construction of all bridges except Tila Khola (rivulet) were completed within January 13, 2021.

Construction of the bridge at Tila rivulet was completed on June 2021 as a contract for the construction was signed late.

Construction of the bridges at Kuwakhola, Kalekhola, Paltada, Kanegad, Guhegad, Dahikhola, Tilakhola, Chhidena Khola, Sinja, Patale Khola, Lumchadi, and Matekhola have been completed. The bridges were constructed at a cost of Rs 424.54 million, according to the Office.

Meanwhile, the Karnali highway has been obstructed due to a landslide at Serighat, Khandachakra municipality-2 of Kalikot district.

The landslide was triggered by incessant rain since Tuesday night. The Road Division Office has employed a dozer for removing the landslide debris from the highway. It is estimated that the highway would be opened for traffic until this evening.

Similarly, a huge landslide triggered by continuous rain has blocked the Karnali Corridor road at Regil of Sanni Tribeni rural municipality. The Karnali Corridor road runs from Kalikot to Humla alongside the Karnali River.

RSS

Publish Date : 21 July 2021 19:16 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Commission is fully ready for election: Acting CEC Bhandari

KATHMANDU: Acting Chief Election Commissioner Ram Prasad Bhandari has expressed

Sudurpashchim Provincial Assembly meeting set for December 26

SUDURPASCHIM: The long-awaited session of the Sudurpashchim Provincial Assembly, which

MCA-Nepal signs contracts worth USD 23.7 million for road maintenance under MCC Compact

KATHMANDU: MCA-Nepal has signed two major contracts worth approximately USD

Elections will be held on time, assures Prime Minister Karki

KATHMANDU: Prime Minister Sushila Karki has called on all political