Dholahiti-Lele road widening sees snail pace



KATHMANDU: The widening drive of Dholahiti-Lele road has not been completed during four years.

Average physical progress of the widening drive was only 55 percent as of mid-January 2021.

Four years ago, a contract was signed to widen the congested road section to 20 meters.

The Kathmandu Valley Road Widening Project said that the drive could not make headway for long due to dispute on the breadth of the road.

Information Officer of the Project Laxman Devkota shared that road widening has not taken place in settlement areas except the forest area along the road section. RSS

Publish Date : 10 February 2021 20:53 PM

Bhim Rawal fumes over Prem Ale’s NCP ticket, says decision made without consultation

KATHMANDU: Sudurpashchim-based NCP leader Dr. Bhim Rawal has expressed strong

Sumana Shrestha set to join Nepali Congress

KATHMANDU: Former Education Minister Sumana Shrestha, who left the Rastriya

Rabi Lamichhane, Balen Shah take stage at Janakpur rally amid massive crowd

KATHMANDU: Rastriya Swatantra Party chairman Rabi Lamichhane and senior leader

Oli questions election security, stays silent on Balen Shah

KATHMANDU: CPN-UML Chair KP Sharma Oli has raised concerns over

Leaders queue for NC tickets, but Gagan and Shekhar remain disconnected

KATHMANDU: As the Nepali Congress prepares for upcoming elections, tensions