KATHMANDU: It seems to take at least three months to restore the water supply from Melamchi to Kathmandu.
The Melamchi Drinking Water Project set a target of bringing about waters from the Sindhupalchowk-based Melamchi River up to Sundarijal by mid-October. The project is to undertake the related works in collaboration with the local levels and other related bodies.
The project was largely damaged by the recent devastating flood in the river. Access roads to the project, bridge and some structures at the construction site had been damaged by the disaster in mid-June, the project said.
According to the project’s Information Officer Rajendra Prasad Pant, they set a target of restoring the water supply if temporary access to the project could be made by re-opening the track and placing a Bailey bridge. But the project is not sure whether the target could be met as the risk of future damage to be caused by monsoon still prevails.
“If we could reach the headwork by mid-September, mud and other depositions caused by the flood inside the tunnel would be cleared off next months. The time to restore the supply system could take long if there is more havoc by the flood,” he said.
The Chinese construction company, Sino Hydro, has been carrying out the remaining works of the project. Among the construction of the structures like the tunnel, headwork and the water treatment center, only the works of the headworks remain.
The project has categorized the repair works to be carried out into two categories – works to be carried out immediately and works to be done in the long run. Construction and repair of the approach road falls under the immediate work.
Project Information Officer Panta said it is estimated that Rs 1 billion would be required for repair work. Works like construction of the road and bridge and clearing the road up to the headwork should be done immediately to supply water from the Melamchi River in Sindhupalchok to Sundarijal of Kathmandu.
Three bodies under the federal government, namely the Department of Roads, Nepali Army and the Melamchi Water Supply Project Board are linked to it as the road and the bridges have to be repaired. The road leading to the project site should be made operational at the earliest with the support of the local level.
For the time being, transport would be operated by constructing a Bailey bridge immediately. A concrete bridge would be constructed in the long run. RSS