Construction of Mistri Khola hydel project in final phase



MYAGDI: Construction of Mistri Khola hydropower project at Annapurna Rural Municipality-4 in Myagdi district has reached its final phase.

Construction works of embankments, canal, and other activities of the 42-MW project has been almost concluded, the project officials said.

Consultant of the project, Engineer Diwakar Khadka, said that overall 98 percent of the construction works of the project were completed.

He added tests of different equipment like the turbine and generator installed at the powerhouse is underway.

The construction activities of the project were started on June 13, 2016. The powerhouse of the project has been constructed on the bank of Kali Gandaki River located at Besigaun of Narchyang.

Publish Date : 17 November 2020 07:47 AM

Displaced children miss school as new academic session begins

KATHMANDU: The new academic session has officially begun from April

Landless citizens to be protected, not displaced: PM Shah

KATHMANDU: Prime Minister Balendra Shah has stated that the government

Eviction drive in Anamnagar turns into public referendum on government action

KATHMANDU: As bulldozers rolled into Devnagar in Anamnagar on Sunday,

RSP unveils ‘scientific’ candidate selection model for upcoming local elections

KATHMANDU: The Rastriya Swatantra Party (RSP) has unveiled a detailed

Revisiting last week: Reform, purge, and debate

KATHMANDU: The past week in Nepal has unfolded as a