59 pc work of Pokhara Regional Int’l Airport completed



POKHARA: The construction work of Pokhara Regional International Airport has been completed by 59 percent.

However, the financial progress of the project of national pride is only 45 percent.

As many as 250 Chinese and 100 Nepali workers are working daily in the project which has not been stopped for a single day during the lockdown.

Construction of 14 buildings including terminal, tower, immigration, customs, hangar, cargo, administrative, fire control, quarantines and rescue is underway, media reports said on Sunday.

Publish Date : 14 June 2020 19:13 PM

Economic Digest: Nepal’s Business News in a Snap

KATHMANDU: Economic Digest offers a concise yet comprehensive overview of

Kathmandu Valley records sharp drop in minimum temperature

KAHTMANDU: Kathmandu Valley experienced a significant drop in its minimum

Mechi Customs Office records Rs 20.14 billion in imports over five months

JHAPA: Goods worth Rs 20.14 billion were imported through the

Gaur schools closed due to extreme cold

RAUTAHAT: Gaur Municipality in Rautahat has announced the closure of

NRB releases today’s foreign currency exchange rates

KATHMANDU: Nepal Rastra Bank (NRB) has published the official foreign