Nyadi Hydro Project stalled as Chinese fail to join work


12 February 2020  

Time taken to read : 2 Minute


  • A
  • A
  • A

LAMJUNG: Coronavirus outbreak in neighboring China has affected the work on the Nyadi Hydropower Project in Lamjung.

According to the project, work has stopped because the Chinese supervisor, engineer and other technicians have not been able to leave their country. “They went home to celebrate the Chinese New Year, but were then stuck there because of the Chinese government’s decision to ban its citizens from leaving the country,” informed Basudev Gadtaula, administrative officer of the project.

According to Gadtaula, there are 61 Chinese nationals working in the project, out of which, 57 had gone to China and only two managed to return. “With 55 of our workers stuck in China, work on the project has stopped for now,” he said.

The project, being constructed on the Nadi River, has been stalled for about a month. “The project is led by the Chinese and in their absence, even the Nepali workers can’t work,” stated Bijay Gurung, the project’s public relations officer.

The 30 MW project is being constructed by the China-based Zhejiang Hydropower Construction and Installation Company Limited.

 

Publish Date : 12 February 2020 11:51 AM

PADT takes back ownership of Dharmashala after 21 years

KATHMANDU: The Dharmashala in Gaushala has returned to the ownership

Khurkot-Ghurmi road section opened for one way traffic

KATHMANDU: The Khurkot-Ghurmi road section along the Madhyapahadi Lokmarga (Mid-hill

Nepal, India sign B2B Framework Agreement on petroleum infrastructure development

KATHMANDU: Nepal and India have reached the B2B Framework Agreement

BP highway unlikely to be fully operational before Dashain: Ministry

KATHMANDU: The Ministry of Physical Infrastructure and Transport announced that

Over 17 thousand people rescued safely

KATHMANDU: More than 17 thousand people, who were stranded in