Nyadi Hydro Project stalled as Chinese fail to join work



LAMJUNG: Coronavirus outbreak in neighboring China has affected the work on the Nyadi Hydropower Project in Lamjung.

According to the project, work has stopped because the Chinese supervisor, engineer and other technicians have not been able to leave their country. “They went home to celebrate the Chinese New Year, but were then stuck there because of the Chinese government’s decision to ban its citizens from leaving the country,” informed Basudev Gadtaula, administrative officer of the project.

According to Gadtaula, there are 61 Chinese nationals working in the project, out of which, 57 had gone to China and only two managed to return. “With 55 of our workers stuck in China, work on the project has stopped for now,” he said.

The project, being constructed on the Nadi River, has been stalled for about a month. “The project is led by the Chinese and in their absence, even the Nepali workers can’t work,” stated Bijay Gurung, the project’s public relations officer.

The 30 MW project is being constructed by the China-based Zhejiang Hydropower Construction and Installation Company Limited.

 

Publish Date : 12 February 2020 11:51 AM

Three arrested for issuing fake citizenship, ID cards, and passports

KATHMANDU: Police have arrested three individuals for allegedly providing false

Shankar Pokhrel elected UML general secretary

  KATHMANDU: Shankar Pokhrel has emerged victorious in the race

KP Sharma Oli wins third term as UML chairperson

KATHMANDU: KP Sharma Oli has been elected for a third

Economy gaining momentum over past three months: Finance Minister Khanal

KATHMANDU: Finance Minister Rameshwor Prasad Khanal has said that Nepal’s

Rising cases of hypertension, asthma, diabetes and heart disease reported in Solukhumbu

KATHMANDU: A growing number of patients have been found suffering