Nyadi Hydro Project stalled as Chinese fail to join work


12 February 2020  

Time taken to read : 2 Minute


  • A
  • A
  • A

LAMJUNG: Coronavirus outbreak in neighboring China has affected the work on the Nyadi Hydropower Project in Lamjung.

According to the project, work has stopped because the Chinese supervisor, engineer and other technicians have not been able to leave their country. “They went home to celebrate the Chinese New Year, but were then stuck there because of the Chinese government’s decision to ban its citizens from leaving the country,” informed Basudev Gadtaula, administrative officer of the project.

According to Gadtaula, there are 61 Chinese nationals working in the project, out of which, 57 had gone to China and only two managed to return. “With 55 of our workers stuck in China, work on the project has stopped for now,” he said.

The project, being constructed on the Nadi River, has been stalled for about a month. “The project is led by the Chinese and in their absence, even the Nepali workers can’t work,” stated Bijay Gurung, the project’s public relations officer.

The 30 MW project is being constructed by the China-based Zhejiang Hydropower Construction and Installation Company Limited.

 

Publish Date : 12 February 2020 11:51 AM

Republican lawmakers optimistic Trump can end Russia-Ukraine war

WASHINGON DC: Top Republican members of the House of Representatives

One killed in jeep-motorcycle collision

DOTI: A 32-year-old man, Lokendra Saud, from Dipayal Silgarhi Municipality-1

Displaced residents of Gorkha return to village after landslide control

GORKHA: Kharungaon, located in Barpak Sulikot Rural Municipality-4 of Gorkha,

Today’s foreign currency exchange rates

KATHMANDU: Nepal Rastra Bank (NRB) has announced the foreign currency

Man killed in wild elephant attack in Jhapa

JHAPA: A man has died in Jhapa following an attack