Bardibas-Simara electric railway continues amid lockdown



BARDIBAS: The work on the Bardibas-Simara electric railway has continued amid the current lockdown.

The railway, a national pride project, has been divided into 17 parts from Bardibas to Rautahat’s Gujara.

Construction of 15 small and big bridges is underway under the section.

Of the total 108-kilometer Bardibas-Simara railway, 50 percent work on 70-kilometer along the part has been completed, according to rail engineer Suresh Sah.

Culvert installation along the section is also underway.

Lalbandi Municipality has coordinated the project, Municipality Mayor Man Bahadur Khadka said.

However, the work on the project in Bardibas is yet to start due to disputes over tree cutting and compensation for the lands acquired for the project, said Bardibas municipality Mayor Bidur Kumar Karki.

Compensation disputes have also led to project work effect at various places in Sarlahi and Rautahat districts.

Publish Date : 06 September 2020 22:38 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Eight thousand families at risk from cold wave in Kanchanpur

KANCHANPUR: The District Administration Office, Kanchanpur, has stated that a

Myagdi’s Changa emerging as a tourist destination

BENI: Changadhuri of Mangala Rural Municipality–5, Arman, rich in natural

India-Nepal Building Partnerships of Progress

India–Nepal relations reflect a deeply integrated economic partnership rooted in

Minister Kharel calls for open discourse on mental health issues

KATHMANDU: Minister for Communication and Information Technology Jagadish Kharel has