Bardibas-Simara electric railway continues amid lockdown



BARDIBAS: The work on the Bardibas-Simara electric railway has continued amid the current lockdown.

The railway, a national pride project, has been divided into 17 parts from Bardibas to Rautahat’s Gujara.

Construction of 15 small and big bridges is underway under the section.

Of the total 108-kilometer Bardibas-Simara railway, 50 percent work on 70-kilometer along the part has been completed, according to rail engineer Suresh Sah.

Culvert installation along the section is also underway.

Lalbandi Municipality has coordinated the project, Municipality Mayor Man Bahadur Khadka said.

However, the work on the project in Bardibas is yet to start due to disputes over tree cutting and compensation for the lands acquired for the project, said Bardibas municipality Mayor Bidur Kumar Karki.

Compensation disputes have also led to project work effect at various places in Sarlahi and Rautahat districts.

Publish Date : 06 September 2020 22:38 PM

Baglung farmers’ woes: Forced to sell oranges at low prices

BAGLUNG: Rural areas of Baglung are currently awash with oranges,

Gold price drops after recent surge

KATHMANDU: Prices of gold and silver have been fluctuating in

Free eye check-up camp in Ghodaghodi: 75 of 384 people diagnosed with cataracts

KAILALI: A high prevalence of cataracts has been observed in

World Meditation Day observed in Kathmandu (Photos)

KATHMANDU: In line with an announcement by the United Nations,

Impact of erratic weather: Paddy production declines in Bhojpur

BHOJPUR: Paddy production in Bhojpur district has declined this year