Kathmandu view tower construction sees dismal progress; 15 percent works in five years



KATHMANDU: The construction of Kathmandu view tower that began around five years back has made dismal progress of 15 percent as of now.

The Kathmandu Metropolitan City (KMC) admitted that the construction progress was only 15 percent during five years since its beginning.

Former chief of KMC Public Private Partnership unit, Dhruba Kafle said that the metropolis should wait for the contracted period as per the rule despite dismal progress in construction.

As per the agreement the construction progress should be almost 75 percent but the target has not been realized. The foundational works under-land have been completed while the task of installing pillar is underway now. With this overall progress of the construction accounts 15 percent.

Now daily 100 workers are being mobilized in the construction work. It may be noted that the KMC had already extended the deadline by a year to facilitate the completion of under-land construction acting on the stipulated rule.

A contract was signed by the KMC and Jaleswor, Swachchhanda and BIKOI Builders around six years back for the construction of the view tower.

The company however had started the construction works since 14 August 2016.

As per the agreement the construction works should be completed by 14 August 2021 but the progress does not indicate much to that end.

Twenty-three ropanies five ana land has been allotted for the construction of the tower. Out of this 40 percent land will be occupied by the tower structure while 60 percent will remain as open space.

The high-rise tower will reflect Nepali art and culture. —

Publish Date : 02 December 2020 12:49 PM

Home Minister orders swift completion of Rasuwagadhi integrated customs building

KATHMANDU: Home Minister Sudan Gurung has directed authorities to expedite

Narayani River embankment works gather pace after years of delays

CHITWAN: Embankment construction along the Narayani River has accelerated after

Education Minister Pokharel vows action against exam paper leakers

KATHMANDU: Minister for Education and Sports, Sasmit Pokharel, has said

17-year-old student allegedly killed over mobile phone dispute in Baglung

GANDAKI: Lajin Thapa, 17, from Badigad Rural Municipality-1 in Baglung

Cooperative victims’ march halted at Shantibatika en route to Singha Durbar

KATHMANDU: A protest march by victims of microfinance institutions towards