Monday, January 19th, 2026

Iwakhola Hydroelectricity Project connected to national grid



PANCHTAR: The power generated from the Panchthar district-based Iwakhola Hydroelectricity Project has been connected to the national grid.

The project with the capacity of generating a maximum of 9.9 megawatts was linked up with the national grid this week through the 132-KV Kabeli Corridor.

According to project promoter company Rairang Hydro Power Ltd’s manager Kubermani Nepali, the project was connected to national grid following test transmission for around a month. He said the production began with one megawatt will be increased gradually as per its technical capacity.

During winter, there will be only three-megawatt production from the project based on the Kabeli River located on the border of Panchthar and Taplejung districts.

An 8.5-kilometer transmission line has been built to connect it to the national grid. Its construction had begun in 2070 BS following the Power Purchase Agreement with Nepal Electricity Authority. But it was intentionally delayed as the construction of the Kabeli Corridor would not complete on time. It cost Rs 1.60 billion to complete the project.

Publish Date : 23 September 2019 13:05 PM

Former Madhesh MP Rahbar Ansari joins RSP, promises new political approach

KATHMANDU: Former Madhesh Province MP Rahbar Ansari, who had left

NC leader Min Bishwakarma announces he will not contest upcoming elections

KATHMANDU: Nepali Congress leader Min Bishwakarma, aligned with the Sher

Durga Prasai arrested over spreading misleading election information

KATHMANDU: Durga Prasai was arrested on Monday in Pokhara. The

Bamdev Gautam returns NCP ticket, announces he will not contest from Bardiya-1

KATHMANDU: Nepali Communist Party (NCP) leader Bamdev Gautam has announced

Bhim Rawal fumes over Prem Ale’s NCP ticket, says decision made without consultation

KATHMANDU: Sudurpashchim-based NCP leader Dr. Bhim Rawal has expressed strong