Nyadi Hydro Project stalled as Chinese fail to join work



LAMJUNG: Coronavirus outbreak in neighboring China has affected the work on the Nyadi Hydropower Project in Lamjung.

According to the project, work has stopped because the Chinese supervisor, engineer and other technicians have not been able to leave their country. “They went home to celebrate the Chinese New Year, but were then stuck there because of the Chinese government’s decision to ban its citizens from leaving the country,” informed Basudev Gadtaula, administrative officer of the project.

According to Gadtaula, there are 61 Chinese nationals working in the project, out of which, 57 had gone to China and only two managed to return. “With 55 of our workers stuck in China, work on the project has stopped for now,” he said.

The project, being constructed on the Nadi River, has been stalled for about a month. “The project is led by the Chinese and in their absence, even the Nepali workers can’t work,” stated Bijay Gurung, the project’s public relations officer.

The 30 MW project is being constructed by the China-based Zhejiang Hydropower Construction and Installation Company Limited.

 

Publish Date : 12 February 2020 11:51 AM

Nepal Tourism Board launches first ‘Safari Mart’ in Chitwan

CHITWAN: The Nepal Tourism Board has formally launched the first-ever

Manohara squatters begin leaving settlement as eviction drive expands

BHAKTAPUR: Residents of the squatter settlement along the Manohara river

Foreign Minister Khanal stresses diplomatic code of conduct for public office holders

KATHMANDU: Minister for Foreign Affairs Shishir Khanal has said that

Chinese and Indian envoys hold separate meetings with Energy Minister on cooperation

KATHMANDU: Energy, Water Resources and Irrigation Minister Biraj Bhakta Shrestha

Eviction drive begins in Gairigaun squatter settlement after Thapathali clearance

KATHMANDU: Authorities have launched an eviction drive in the squatter