Upper Bhotekoshi begins commercial production



CHAUTARA: The Sindhupalchowk-based 45-megawatt Bhotekoshi Hydropower Project has started its commercial production.

The project has started the commercial power generation following a two-week-long test transmission, according to project chief executive officer Bikram Sthapit.

The power generated from the Bhotekoshi Hydropower Project has been connected to the national grid through the Lamosanghu-based substation.

The reconstruction of the project, which remained closed due to the 2015 April earthquake and subsequent floods and landslides, was completed recently.

The current production of the project on average is 22-25 megawatt each day.

A Chinese Company Sinohydro Bureau 11 was awarded the project contract in 2074 BS at the cost of Rs seven billion.

Publish Date : 22 December 2019 21:23 PM

Foreign Minister says Nepal committed to resolving border disputes through dialogue

KATHMANDU: Foreign Minister Shishir Khanal has said Nepal remains committed

Rai accuses Finance Minister of undermining Parliament through tax rate revisions

KATHMANDU: Nepali Congress Whip Nishkal Rai has accused Finance Minister

Finance Minister Wagle defends tax reforms, rejects allegations of irregularities

KATHMANDU: Finance Minister Swarnim Wagle has defended recent changes to

Home Minister says agencies directed to remain prepared for disasters

KATHMANDU: Home Minister Sudan Gurung has said that all concerned

Over 2,200 drivers penalized for traffic violations in Kathmandu Valley

KATHMANDU: Traffic police in the Kathmandu Valley took action against