Eleven kilometers of Nagdhunga-Malekhu road blacktopped



CHITWAN: The 11-kilometer Nagdhunga-Malekhu section of the Prithvi Highway has been blacktopped, with eight kilometers completed last year and an additional three kilometers finished this year.

According to Bijay Darai, Project Engineer of the Nagdhunga-Muglin Road Project, 40 percent of the third phase, including Kurintar, Fisling, Charaudi, and parts of Bishaltar, has been blacktopped so far.

Blacktopping work is ongoing in Bandre in Dhading, while bases and subbases have been laid in the Fisling and Jawang Khola areas. Of the six bridges in this section, construction is underway at Hugdi and Charaudi. Darai said the project is committed to ensuring there is no shortage of construction materials.

Although materials have been brought from Charaudi, Benighat, and Ichchakamana in Dhading, he expressed concern that supply shortages could persist for some time. The 38-kilometer road section is being upgraded with a World Bank loan of Rs 4.8059 billion.

Publish Date : 15 February 2026 16:03 PM

Bhote Koshi floods: 677 transport workers unaccounted for

KATHMANDU: The Nepal Truck Transport Entrepreneurs Federation has reported that

29th memorial day of Ganesh Man Singh being observed today

KATHMANDU: The Nepali Congress, its sister organizations and well-wishers are

US approves USD 24.3 billion sale of 48 F-35 fighter jets to Saudi Arabia

WASHINGTON DC: The US Department of State on Thursday (Local

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of

Birendrabhakta to continue tongue-piercing ritual

BHAKTAPUR: Birendrabhakta Gaju Shrestha, a 39-year-old resident of Balkumari, Madhyapur