Sunday, December 14th, 2025

Contract for long-delayed Kankai Bridge in Jhapa terminated



KATHMANDU: The contract for constructing the Kankai Bridge, which has remained incomplete for 14 years, connecting Jhapa Rural Municipality-2 and Gauriganj Rural Municipality-1 along the Postal Highway, has been officially terminated.

On Thursday, the Planning Office, Itahari, under the Postal Highway Directorate of the Department of Roads, ended the contract with Pappu Mahadev Khimti Joint Venture (JV), which had been awarded the project in May 2011.

The 723-meter-long bridge, planned under a design-and-build model, was initially scheduled for completion by July 2015. Despite five extensions, construction progress has reached only about 56 percent. The contract was valued at Rs 340million, including taxes, and the Performance Guarantee of Rs 17.1 million will now be forfeited.

The Planning Office had given the contractor a 15-day notice in late October, seeking clarification on delays. “The explanation provided by the contractor was unsatisfactory, and they failed to present a credible plan, allocate resources, or commit to completing the work. Therefore, the contract has been terminated in accordance with the Public Procurement Act,” said Yubaraj Pokhrel, Chief of the Planning Office, Itahari.

The remaining work will be completed using government funds, and the contractor has also been recommended to be blacklisted. Officials have called on the contractor to be present within 15 days for updated measurements and financial settlement; otherwise, the office will proceed with its own assessment.

Energy, Water Resources and Irrigation Minister Kulman Ghising had inspected the site in mid-October and assured local residents of swift action. He stressed that the practice of awarding contracts without completion must end. The bridge’s delay has caused severe hardship for residents and hindered trade, business, and tourism.

Of the 19 planned spans, eight have been completed. Among the remaining 11, two have girders installed, six have foundations laid, and three are still pending foundation work. Technical tests had revealed flaws in earlier construction, which were partially corrected by the contractor. With the contract deadline expired, the Planning Office has now taken over responsibility to complete the long-stalled project.

Publish Date : 27 November 2025 11:26 AM

CPN-UML election battle: Oli and Pokharel camps finalize strategies

KATHMANDU: Competition between CPN-UML Chair KP Sharma Oli and Senior

At least 12 dead in mass shooting at Sydney’s Bondi Beach

SYDNEY: At least 12 people have been killed in a

State responsible for promotion of inclusion: PM Karki

KATHMANDU: Prime Minister Sushila Karki asserted that it is the

UML Convention to extend by 3 days

KATHMANDU: The election schedule for the 11th general convention of

President asks govt. to solely focus on election

KATHMANDU: President Ramchandra Paudel has suggested that the government should