Kaligandaki Corridor: Blacktopping of Lasti–Beni section underway



MYAGDI: Blacktopping work has commenced on the Lasti–Beni stretch of the Kali Gandaki Corridor, a key road link connecting Maldhunga–Beni–Mustang with the national highway network.

According to Engineer Bishnu Chapagai, Information Officer at the Beni–Jomsom–Korala Road Project, the blacktopping process from Farse toward Beni began today. “Out of the 13-kilometer-long Maldhunga–Beni road, around two kilometers in the landslide-affected area have already been graded,” he said.

Earlier, approximately five kilometers of the road—from Maldhunga in Kushma Municipality-1, Parbat, to Farse in Jaljala Rural Municipality-8—had already been blacktopped.

A contract worth Rs 528.6 million was signed in April 2021 for widening the Maldhunga–Beni section to 11 meters and completing grading and blacktopping works using modern asphalt technology.

Once completed, the project is expected to significantly improve connectivity, reduce travel time, and boost economic activities along the corridor.

Publish Date : 13 November 2025 09:11 AM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Ujyalo Nepal to support Mahabir Pun in Myagdi

KATHMANDU: The Ujyalo Nepal Party has decided to support former

Petroleum imports from Kakarbhitta exceed Rs 9.77 billion in six months

JHAPA: Petroleum products worth more than Rs 9.77 billion have

158 polling stations classified as highly sensitive in Sarlahi

BARHATHWA: As many as 158 polling stations in Sarlahi have