Chinese contractor company of Narayangadh-Butwal road section fails to meet deadline yet again; seeks another extension


08 February 2024  

Time taken to read : 3 Minute


  • A
  • A
  • A

NAWALPUR: Failing to meet the deadline of expanding the Narayangadh-Butwal road section under the East-West Highway, the contractor company — China State Construction Engineering Corporation Limited — has sought an extension of the deadline by another nine months.

It should be noted that the construction wor has been completed by only 46 percent in five years since the work began.

The contract of the road project has already been extended twice but the work is far from over according to the Information Officer of Narayangadh-Butwal Road Extension Plan, Eastern Section, Engineer Shiva Khanal.

Out of the total 114 km of road from Narayangadh to Butwal, 65 km of road falls in the eastern section.

According to Khanal, the road expansion work has not been able to accelerate due to the fact that the contractors are not working according to the plans they have made.

“We are constantly putting pressure to work according to the schedule and to complete the project on time”, he said.

The China State Construction Engineering Corporation Limited was given the contract to complete the expansion project to be completed in four years, after starting the work in 2075 B.S.

Meanwhile, contract co-manager of China State Construction Engineering Corporation Limite, Rakesh Jha, said that the road expansion work cannot be completed during the second extension period and that the deadline should be extended by one more year.

The road expansion work was delayed due to various reasons including the current weather that is hampering the black topping of the finish section of the road.

The work of moving water supply and electricity poles as well as 30 KV transmission lines in Siji, Gandakot and Dumkibas areas are yet to be completed, he said.

After the expansion of the existing two-lane road, the highway will be seven by seven meters on both sides.

A service lane of 6 meters each will also be constructed in the market area. Information Officer Khanal said that the 42.7 km section of the road will have four lanes, while the southern section will have three lanes for about five km.

In this section, 12 big bridges and 22 small bridges are under construction.

The construction of this section started with 85 percent loan support from the Asian Development Bank and the total cost of this section is 9.38 billion rupees.

Publish Date : 08 February 2024 07:48 AM

Gold prices drop by Rs 15,900 per tola

KATHMANDU: Gold prices have decreased significantly in the Nepali market

Put efforts to build civilized and violence-free society: PM Oli

KATHMANDU: Prime Minister KP Sharma Oli extended his best wishes

The End of the Liberal West

We all think, speak, and write within certain intellectual frameworks

Environment Department asks public to refrain from burning plastic waste

KATHMANDU: The Department of Environment has urged the public to

Students fall ill due to cold weather in Baglung

BAGLUNG: Students in Dhorpatan, Baglung, are falling ill as cold