Rahughat hydel project sees 60 percent construction in 14 years



MYAGDI: Fourteen years into construction, the under-construction 40-megawatt-capacity Rahughat hydropower project has seen 60 percent of construction work.

The construction of the project was started in 2066 BS by the Nepal Electricity Authority (NEA) with a concessional loan of USD 67 million from the Export-Import Bank of India (Exim Bank) and joint investment of the NEA and the Government of Nepal.

After the contract with the old contractor, IVRCL was terminated in 2072 BS due to the weak economic situation, the construction of the project advanced under the company’s concept and engineering procurement and contract (EPC) format.

The project should have been completed in 2070 BS according to the previous schedule and agreement. The civil contractor Jaiprakash Associate (JP), which signed the contract of Rs 6 billion with the completion target being 2074 BS, has not been able to complete the project within the stipulated time.

Overall 60 percent physical progress and 45 percent financial progress have taken place so far, said the project manager Raj Bista. “The project aimed to operate from January 2023. The contractor could not meet the completion target due to COVID-19 and other disasters. So, the contract agreement has been extended until 17 October 2024,” he said.

The old contractor, IVRCL, did 10 percent of the work in eight years. The JP Company, which started works on construction of the access road in 2075 BS and a tunnel in 2076 BS, has so far constructed a 61-meter deep surge shaft, a 329-meter bottom pressure shaft, a 654-meter-long four access roads leading to the main tunnel and a 196-meter vertical tunnel.

Out of six km and 270 meters long tunnels, 5,162 meters have been completed so far. One thousand one hundred and eight meters of the tunnel remains to be dug.

RSS

Publish Date : 24 September 2023 15:37 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Commission is fully ready for election: Acting CEC Bhandari

KATHMANDU: Acting Chief Election Commissioner Ram Prasad Bhandari has expressed

Sudurpashchim Provincial Assembly meeting set for December 26

SUDURPASCHIM: The long-awaited session of the Sudurpashchim Provincial Assembly, which

MCA-Nepal signs contracts worth USD 23.7 million for road maintenance under MCC Compact

KATHMANDU: MCA-Nepal has signed two major contracts worth approximately USD

Elections will be held on time, assures Prime Minister Karki

KATHMANDU: Prime Minister Sushila Karki has called on all political