Friday, November 22nd, 2024

Hulaki Road: Construction incomplete even after extension of deadline five times


06 April 2023  

Time taken to read : 3 Minute


  • A
  • A
  • A

MAHENDRANAGAR: Construction of the Hulaki Road aka the Postal Highway here has not been completed even after six years of the deadline.

The construction of 62 kilometers section of the highway from Dokebazaar to Bedkot of Kanchanpur district should have been over in 30 months had the construction works moved ahead smoothly.

The contract for this was signed in March 2017. Twenty-six kilometers of the section of the highway in Kanchanpur district remain to be blacktopped.

Engineer at the Hulaki Highway Project Office, Deepak Sunar accepted that there has been a delay in the construction of the highway.

“The delay was due to the COVID-19 pandemic and taking approval from the National Park Office. The construction is not complete yet even after extending the deadline for five times,” he said.

Construction of 62 kilometers of the Hulaki Road was begun after awarding the contract in three phases.

The first phase included the 20 kilometres road construction from Dokebazaar to Belauri.

Ninety percent works have been completed on this section. However, the construction remains uncompleted in the remaining two sections.

The Sharma-Rajendra JV had been awarded the contract for construction of the road in the first package at a cost of Rs 364.7 million.

The estimated cost for construction of the 20 kilometres road from Belauri to Beldandi under the second package is Rs 414.1 million.

Only nine kilometres of the road in this section has been blacktopped so far, Sunar said.

The construction has halted at Chui area on this section due to the obstruction from the Indian side.

The Indian security bodies have obstructed blacktopping the road in this location claiming the road lies within the Indian territory.

The Babahansa Siddhisai JV, the construction company responsible for carrying out the construction under the second package, has hardly completed 50 percent of the work.

Similarly, only eight and half kilometres of the 22-kilometre section of the highway from Beldandi to Daiji has been blacktopped under the third package in a span of six years.

“The deadline for completing the works under the second and third package has been extended till mid-July this year. Only 36 kilometres of the highway has been asphalted in six years since the deadline was last extended,” Sunar lamented.

The local municipalities through which the road passes have been exerting pressure from time to time for the timely completion of the construction works.

Publish Date : 06 April 2023 20:39 PM

GP Koirala Hospital to begin dialysis service

TANAHU: The GP Koirala National Centre for Respiratory Diseases based

Weather expected to be clear today

KATHMANDU: The Department of Hydrology and Meteorology has reported a

Three youths killed in high-speed motorcycle collision

BIRATNAGAR: Three youths died, and another was seriously injured following

Economic Digest: Nepal’s Business News in a Snap

KATHMANDU: Economic Digest offers a concise yet comprehensive overview of

Ruling CPN-UML demonstrating in Kathmandu today

KATHMANDU: The ruling CPN-UML is set to demonstrate its strength