35 percent physical progress achieved in Nagdhunga tunnel



KATHMANDU: The physical progress in the Nagdhunga tunnel way has reached around 35 percent while the economic progress is 43 percent.

The Nagdhunga Tunnel Way Project said 76 percent of the road construction was finished while the progress on dam is 37 percent. So far, construction of overpass is completed and flyover is under construction.

Development of two underpasses out of three is done and three box culverts are also constructed. Likewise, two out of three bridges have also completed. Till date, 1.1 km of the main tunnel is completed out of its total 2.6 km length.

The Project further shared that development of 1,384 meters of exit tunnel is finished out of total 2,557 meters. The Project has already completed the working audit as well. Similarly, 48 out of 128 meters of the cross passage is over.

The Nagdhunga Tunnel, which is the first of its kind in the country, is being developed with the concessional loan assistance from Japan International Cooperation Agency (JICA).

Publish Date : 07 April 2022 21:08 PM

HoR approves govt policy and program despite opposition obstruction

KATHMANDU: The House of Representatives (HoR) on Thursday approved the

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

UML also boycotts House session amid escalating opposition protest

KATHMANDU: Opposition protests in the House of Representatives intensified on

Finance Minister Wagle says policy and programme reflect shared vision of all parties

KATHMANDU: Finance Minister Dr Swarnim Wagle has claimed that the

Bandipur Hospital receives equipment worth around Rs 4 million

TANAHUN: Various organizations and businessmen have donated modern health equipment