Construction of Ranke-Rabi-Bhedetar road to be accelerated: Minister Nembang



PANCHTHAR: Minster for Physical Infrastructure and Transport Basanta Kumar Nembang pledged to take proper decision soon to speed up the construction of Ranke-Rabi-Bhedetar road.

Minsiter Nembang, who came to Panchthar for on-site inspection after sluggish progress on road construction, said the construction works would take headway.

The road being constructed with the funding of Indian government has so far made 12 percent physical progress which has normally to be 43 percent.

Making inspection of the road construction with slack of progress, Minster Nembang said appropriate decision would be made to expedite the construction works.

“Discussion was held with the Indian government through our Ministry of Foreign Affairs in this regard. Only options are whether to terminate the contract or to ensure substantial progress in definite period of time”, the minister added.

Minister Nembang said, “The Ministry would take decision required to speed up the construction of the road”.

Publish Date : 14 December 2020 11:08 AM

Congress focused on changing the country, let’s unite for elections: NC President Thapa

KATHMANDU: Nepali Congress President Gagan Kumar Thapa has said that

Cleanup carried out at Pashupati area in preparation for Maha Shivaratri

KATHMANDU: Cleanup activities have been carried out in the sacred

RPP demands immediate release of Durga Prasai

KATHMANDU: The Rastriya Prajatantra Party (RPP) has urged the government

Strong security arrangements ensured for the election: Home Minister

NUWAKOT: Home Minister Om Prakash Aryal has said that strong

Jhapa–4 becomes a testing ground for old and new political forces

SURUNGA: Construction of a bridge over the Kankai River, connecting