Deadline for Dharahara reconstruction extended by nine months



KATHMANDU: The deadline for the reconstruction of Dharahara Tower has been extended by nine months.

The National Reconstruction Authority (NRA) extended the deadline by nine months despite Raman Construction’s demanded an extension by 21 months, arguing that the COVID-19 crisis hindered the construction works.

NRA had signed an agreement with Raman Construction to complete the construction of the tower by October 6, 2020.

Raman Construction’s Project Manager Shyam Chandra Shrestha said that the work was affected due to the lockdown and as the site of the main museum has been just acquired.

The devastating 2015 earthquake had damaged the historic tower.

Publish Date : 09 October 2020 19:16 PM

Squatters’ association announces phased protest for land rights

KATHMANDU: The All Nepal Squatters Association has announced a phased

Kathmandu air quality improves after rainfall, drops to moderate level

KATHMANDU: Air quality in the Kathmandu Valley has shown notable

Supreme Court orders swift probe into transitional justice complaints

KATHMANDU: The Supreme Court has issued a mandamus order directing

Opposition parties unite against Balen-led government’s recent decisions

KATHMANDU: Major opposition parties represented in Parliament have formed a

Tribhuvan University officials resign following ordinance move

KATHMANDU: Senior officials of Tribhuvan University have tendered their resignations