HETAUDA: Construction of the Kathmandu-Terai/Madhes Expressway, being developed under the management of the Nepali Army, has achieved 51 percent physical progress.
Project Chief Brigadier General Bharat Lal Shrestha shared the update during a breakthrough ceremony held today to mark the completion of excavation work on the 3,454-metre-long Mahadevtar Tunnel, the longest tunnel along the expressway.
He said construction activities had gained momentum since the Nepali Army was entrusted with managing the strategically important national pride project.
Although the project faced delays at various stages in the past, Shrestha said some land acquisition issues remain unresolved along the Khokana-Dukuchhap section in Lalitpur. Efforts are underway to address the problems affecting the 6.5-kilometre stretch, after which the contract management process will move forward, he added.
According to Shrestha, construction progress is expected to accelerate further in the coming days, as most of the project’s substructure works have already been completed.
The Nepali Army said six of the 14 tunnels being constructed at seven locations along the expressway have been completed. These include tunnels at Dhedre, Lendanda and Mahadevtar, while work on the remaining eight tunnels at four other locations is ongoing.
President Ram Chandra Paudel, Minister for Infrastructure Development Sunil Lamsal, the Chief of the Army Staff, ambassadors of China and South Korea, Bagmati Province Chief Deepak Prasad Devkota, Makawanpur Chief District Officer Basanta Adhikari, and representatives of consulting firms and construction companies attended the breakthrough ceremony.