DHADING: Reconstruction and repair work on the Mahadev Phant–Chhabise section of the Galchhi–Rasuwagadhi road has been accelerated after the Trishuli River damaged the road following flooding in Rasuwa.
The road section was weakened after heavy flooding on August 26 caused a significant increase in the river’s flow, resulting in severe erosion along the lower section of the road in the Mahadev Phant–Chhabise area.
Continuous river erosion caused parts of the road to sink, forcing the complete closure of regular traffic along the affected section.
Following the disruption, construction and technical teams inspected the damaged area and began work with the aim of restoring road access as soon as possible. Work is underway to strengthen the road foundation, fill damaged sections and construct alternative structures to prevent further erosion from the river.
Although the main road remains blocked, travellers can still use an alternative route to travel from Galchhi to Devighat. However, the closure of the main road has affected long-distance passengers, local residents and vehicles transporting goods.
The flood in Rasuwa caused extensive damage to roads, bridges and other infrastructure along the Trishuli River corridor, making transportation difficult at several points along the Galchhi–Rasuwagadhi road. In areas affected by river erosion, authorities are working to manage traffic through alternative routes and temporary structures.
As the road connects to Rasuwagadhi, Nepal’s northern border point with China, the disruption has affected not only local travel but also commercial and freight transportation. Passengers and vehicles carrying goods towards Rasuwa have been required to use alternative routes.
The construction team has said it is working to temporarily reopen the damaged section as quickly as possible while considering river flow, weather and geographical conditions. A long-term plan will then focus on building a safer and more durable road structure.