Defence Ministry reports over 80% progress in annual targets; key infrastructure projects show mixed results



KATHMANDU: The Ministry of Defence has reported more than 80 percent progress against its annual target for the current fiscal year, according to the quarterly review and the Ministry-level National Development Problem Solving Committee meeting held today.

The review showed full physical progress in several key road projects under the ministry, including the Koshi Corridor (Chamthang–Ghongghappa) Road Project, the Karnali Road Project, and the Benighat–Aarughat–Larke Bhanjyang Road Project, all of which have reached 100 percent completion for the period under review.

Other major projects have also recorded strong progress. The Mahakali Corridor (Tusharpani–Tinker) Road Project has achieved 82.99 percent progress, while the National Chure Conservation Programme stands at 80 percent.

However, progress has been relatively slower in some flagship initiatives. The Kathmandu–Terai/Madhes Fast Track Road Project has reached 34.4 percent, the National Defence University stands at 35.73 percent, and the Bunker-to-Barracks Project has recorded 23.50 percent progress.

Chief of Army Staff Ashok Raj Sigdel noted that limited budget availability for opening track roads has constrained work capacity. He also stressed that the military’s primary focus remains the completion of the fast track project, expressing hope that current challenges would ease going forward.

Defence Ministry Secretary Kedar Nath Sharma said that while overall progress is satisfactory in national terms, several obstacles cannot be addressed by the ministry alone, highlighting the need for stronger inter-ministerial coordination and support.

National Defence University Chairman Balananda Sharma urged the government to move forward with the relevant bill for the university’s operation and to improve access road infrastructure. During the meeting, Ministry Joint Secretary Krishna Paudel presented the progress review, while representatives from various ministries pledged coordination and support to address outstanding challenges.

Publish Date : 05 May 2026 21:57 PM

Floods and landslides block major highways nationwide

KATHMANDU: Floods, landslides, and road erosion triggered by continuous rainfall

Mustang local level calls for participation from all 753 local units in climate conference

KATHMANDU: Gharpajhong Rural Municipality of Mustang has invited all 753

Midnight flood in Modikhola washes away two bridges

POKHARA: A massive flood in the Modikhola River along the

Thawang landslide: 10 bodies recovered, three still missing

ROLPA: The bodies of 10 people who died in a

Two metal bridges swept away in Modi Khola flood

KATHMANDU: A massive flood in the Modi Khola along the