Muglin–Pokhara Khairenitar west section: Blacktopping begins in Jamune



DAMAULI: Blacktopping work has begun in Jamune Bazaar under the Muglin–Pokhara Road Project (West Section).

Of the total 39 kilometers in this section, 36.8 kilometers have already been blacktopped, while the remaining segments are being completed at an accelerated pace.

According to Krishna Kunwar, head of the Muglin–Pokhara Road Project (West Section), a few stretches—including Mauriodar in Myagde, Dulegowda in Shuklagandaki, Vijaypul in Kaski, and the area near Pokhara University—are still awaiting blacktopping.

Out of the 12 bridges planned in this section, 10 have been completed. Similarly, 92 out of 100 culverts have been constructed. The project, which began with a total budget of Rs 7.4 billion, is targeted for completion by the upcoming month of December.

Publish Date : 29 August 2025 23:43 PM

PM Karki, UML Chairman Oli hold talks in Baluwatar

KATHMANDU: Amid growing political tension over the upcoming elections, Prime

Rastriya Swatantra Party chief Rabi Lamichhane heads to Chitwan after recovery

KATHMANDU: Rastriya Swatantra Party (RSP) Chairperson Ravi Lamichhane is traveling

Govt revises multi-year project funding approval process

KATHMANDU: The government has revised the process related to contracts

Gold price drops by Rs 9,500 per tola

KATHMANDU: The price of gold has declined in the domestic

Election Commission issues vehicle permit guidelines for election

KATHMANDU: The Election Commission has issued the “Vehicle Permit Guidelines,