Muglin–Pokhara Khairenitar west section: Blacktopping begins in Jamune



DAMAULI: Blacktopping work has begun in Jamune Bazaar under the Muglin–Pokhara Road Project (West Section).

Of the total 39 kilometers in this section, 36.8 kilometers have already been blacktopped, while the remaining segments are being completed at an accelerated pace.

According to Krishna Kunwar, head of the Muglin–Pokhara Road Project (West Section), a few stretches—including Mauriodar in Myagde, Dulegowda in Shuklagandaki, Vijaypul in Kaski, and the area near Pokhara University—are still awaiting blacktopping.

Out of the 12 bridges planned in this section, 10 have been completed. Similarly, 92 out of 100 culverts have been constructed. The project, which began with a total budget of Rs 7.4 billion, is targeted for completion by the upcoming month of December.

Publish Date : 29 August 2025 23:43 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Special convention factions stand firm: No consensus until Deuba steps down

KATHMANDU: The closed session of the Nepali Congress’ second special

US revokes over 100,000 visas, including thousands of student and specialized visas

WASHINGTON: The US Department of State has revoked more than

Electronic cigarettes worth Rs 22.4 million seized at Korala border

KATHMANDU: Electronic cigarettes (vapes) worth Rs 22.4 million were seized

Nepali Congress executive committee meeting postponed, rescheduled for tomorrow at 8 a.m.

KATHMANDU: The Nepali Congress Central Executive Committee meeting, which began