Kamala River bridge construction stalled for 14 years



SIRAHA: The construction of a 469-metre bridge over the Kamala River, meant to connect Siraha and Dhanusha districts, has remained incomplete for 14 years, forcing locals to rely on a risky makeshift wooden bridge.

The project, awarded in 2011 with a three-year completion deadline, was first contracted to Pappu-Lumbini JV. Pappu Construction was later blacklisted, and Lumbini Builders took over, but work has been halted for the past month, with the company citing unpaid insurance claims for flood damage.

Locals say the delay has caused severe hardship. “The wooden bridge is risky, but we have no choice,” said Prabin Yadav of Siraha-6. Motorcycle riders are reportedly charged up to Rs 50 to cross, despite the municipality stating it should be free.

Postal Highway Directorate Planning Office engineer Ranjit Kumar Raya said the process has begun to blacklist Lumbini Builders for failing to resume work.

Publish Date : 11 August 2025 21:57 PM

Revisiting Last Week: Politics, Pressure and Policy Promises

KATHMANDU: The past week offered a revealing snapshot of Nepal’s

Economic Digest: A Snapshot of Nepal’s Business News

KATHMANDU: Economic Digest presents a brief yet comprehensive roundup of

Heavy rain likely in Koshi, Bagmati, Gandaki and Lumbini

KATHMANDU: Heavy rainfall accompanied by thunder and lightning is likely

Deuba digs in as Gagan pushes ahead, NC split looms

KATHMANDU: A widening rift between Gagan Thapa and Sher Bahadur

PM Shah to return to Kathmandu after three-day private visit

KATHMANDU: Prime Minister (PM) Balendra Shah has been in Gandaki