Kamala River bridge construction stalled for 14 years



SIRAHA: The construction of a 469-metre bridge over the Kamala River, meant to connect Siraha and Dhanusha districts, has remained incomplete for 14 years, forcing locals to rely on a risky makeshift wooden bridge.

The project, awarded in 2011 with a three-year completion deadline, was first contracted to Pappu-Lumbini JV. Pappu Construction was later blacklisted, and Lumbini Builders took over, but work has been halted for the past month, with the company citing unpaid insurance claims for flood damage.

Locals say the delay has caused severe hardship. “The wooden bridge is risky, but we have no choice,” said Prabin Yadav of Siraha-6. Motorcycle riders are reportedly charged up to Rs 50 to cross, despite the municipality stating it should be free.

Postal Highway Directorate Planning Office engineer Ranjit Kumar Raya said the process has begun to blacklist Lumbini Builders for failing to resume work.

Publish Date : 11 August 2025 21:57 PM

RSP’s first general convention exposes growing pains and internal contradictions

KATHMANDU: The first general convention of the Rastriya Swatantra Party

Two children killed in car accident in Tanahun

KATHMANDU: Two children have died after being struck by an

Snake rescuer warns against social media stunts, urges public awareness over viral content

KATHMANDU: Veteran snake rescuer Yamlal Kandel has warned that the

Timely monsoon boosts paddy transplantation across Kaski

KASKI: Paddy transplantation has gathered pace in Kaski after the

Traffic violations generate Rs 2.11 million in revenue in a day

KATHMANDU: Traffic police took action against 2,102 motorists for violating