Kamala River bridge construction stalled for 14 years



SIRAHA: The construction of a 469-metre bridge over the Kamala River, meant to connect Siraha and Dhanusha districts, has remained incomplete for 14 years, forcing locals to rely on a risky makeshift wooden bridge.

The project, awarded in 2011 with a three-year completion deadline, was first contracted to Pappu-Lumbini JV. Pappu Construction was later blacklisted, and Lumbini Builders took over, but work has been halted for the past month, with the company citing unpaid insurance claims for flood damage.

Locals say the delay has caused severe hardship. “The wooden bridge is risky, but we have no choice,” said Prabin Yadav of Siraha-6. Motorcycle riders are reportedly charged up to Rs 50 to cross, despite the municipality stating it should be free.

Postal Highway Directorate Planning Office engineer Ranjit Kumar Raya said the process has begun to blacklist Lumbini Builders for failing to resume work.

Publish Date : 11 August 2025 21:57 PM

Gold and silver prices increase

KATHMANDU: The prices of gold and silver have increased in

Buddha Circuit to connect Panauti, Namobuddha and Temal

KAVREPALANCHOK: The ‘Buddha Circuit’ is set to be developed as

NRNs in Texas contribute Rs 21.5 million for Bhote Koshi flood survivors

TEXAS: The Nepali community in Texas has contributed Rs 21.517

Motorcycle rider dies in road accident

SUNSARI: A motorcycle rider died in a road accident in

Finance Minister Wagle to meet Indian Foreign Minister Jaishankar today

KATHMANDU: Finance Minister Dr Swarnim Wagle, who is on a