Kamala River bridge construction stalled for 14 years



SIRAHA: The construction of a 469-metre bridge over the Kamala River, meant to connect Siraha and Dhanusha districts, has remained incomplete for 14 years, forcing locals to rely on a risky makeshift wooden bridge.

The project, awarded in 2011 with a three-year completion deadline, was first contracted to Pappu-Lumbini JV. Pappu Construction was later blacklisted, and Lumbini Builders took over, but work has been halted for the past month, with the company citing unpaid insurance claims for flood damage.

Locals say the delay has caused severe hardship. “The wooden bridge is risky, but we have no choice,” said Prabin Yadav of Siraha-6. Motorcycle riders are reportedly charged up to Rs 50 to cross, despite the municipality stating it should be free.

Postal Highway Directorate Planning Office engineer Ranjit Kumar Raya said the process has begun to blacklist Lumbini Builders for failing to resume work.

Publish Date : 11 August 2025 21:57 PM

The Growing Strategic Reach of China’s Cyber Operations

In October 2026, Dutch intelligence agencies warned that Chinese state-sponsored

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Defending champions Lumbini Lions become first team to qualify for NPL playoffs

KATHMANDU: Defending champions Lumbini Lions have become the first team

Jensen Huang resigns as Nvidia CEO

NEW DELHI: The aftermath of the alleged ‘Chinese spy scandal’

High-level RSP delegation to visit China

KATHMANDU: A high-level delegation of the Rastriya Swatantra Party (RSP)