Kamala River bridge construction stalled for 14 years



SIRAHA: The construction of a 469-metre bridge over the Kamala River, meant to connect Siraha and Dhanusha districts, has remained incomplete for 14 years, forcing locals to rely on a risky makeshift wooden bridge.

The project, awarded in 2011 with a three-year completion deadline, was first contracted to Pappu-Lumbini JV. Pappu Construction was later blacklisted, and Lumbini Builders took over, but work has been halted for the past month, with the company citing unpaid insurance claims for flood damage.

Locals say the delay has caused severe hardship. “The wooden bridge is risky, but we have no choice,” said Prabin Yadav of Siraha-6. Motorcycle riders are reportedly charged up to Rs 50 to cross, despite the municipality stating it should be free.

Postal Highway Directorate Planning Office engineer Ranjit Kumar Raya said the process has begun to blacklist Lumbini Builders for failing to resume work.

Publish Date : 11 August 2025 21:57 PM

Deepak Khadka admitted to hospital

KATHMANDU: Arrested former minister and Nepali Congress leader Deepak Khadka

Domestic violence cases raise questions over local governments’ role in crime prevention

KATHMANDU: A series of recent incidents of domestic violence across

Landslide obstructs Mechi Highway

JHAPA: The Mechi Highway, which had been operating on a

Public Procurement Act overhaul planned within a month

KATHMANDU: The newly formed government led by Prime Minister Balendra

Habeas corpus petition on Lekhak’s arrest assigned to Justice Kumar Regmi

KATHMANDU: A habeas corpus petition filed against the arrest of