Narayangadh-Muglin road to remain closed in the afternoon for another three weeks



MUGLIN: The Narayangadh-Muglin road section is set to remain closed in the afternoons for an additional three weeks, following the delay in completing the rock-breaking work for the construction of a bridge over the Tuin River.

This closure decision was made during a meeting of the District Security Committee at the District Administration Office Chitwan.

Engineer Krishna Acharya, the information officer of Nagdhuga-Muglin Road Project West Section-Narayangadh-Muglin, confirmed the closure, stating that the road closure is necessary to facilitate the completion of the pending construction work.

Among the 19 bridges planned for the road, four were successfully built four years ago, while the remaining 15 bridges are part of a concurrent construction contract.

Publish Date : 02 February 2024 07:22 AM

Two rupees for survival: How food and power costs are breaking Pakistani households

A new government survey has delivered a stark assessment of

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

CIAA seizes mobile phones of 27, including Transport Office Chief

KATHMANDU: The Commission for the Investigation of Abuse of Authority

India gifts vehicles to Nepal government for upcoming House of Representatives election

KATHMANDU: The Government of India has gifted vehicles to Nepal

Rabi Lamichhane hospitalised after leg injury

KATHMANDU: Rastriya Swatantra Party (RSP) chairperson Rabi Lamichhane has been