Ranke-Rabi-Bhedetar road sees dismal progress in 50 months



DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

JSP-N’s Ram Ashish Yadav elected Speaker of Madhesh Provincial Assembly

KATHMANDU: Ram Ashish Yadav of Janata Samajwadi Party Nepal (JSP-N)

Rabi lashes out at Congress and UML: Those who drank children’s blood should not lecture us

KATHMANDU: Rastriya Swatantra Party (RSP) chair Rabi Lamichhane has accused

NC recommends three names from Kalikot

KALIKOT: The Nepali Congress District Working Committee in Kalikot has

NEPSE index drops by 19 points

KATHMANDU: The Nepal Stock Exchange (NEPSE) index experienced a double-digit

More people in Chitwan taking non-resident citizenship

CHITWAN: The number of people acquiring non-resident Nepali citizenship in