Ranke-Rabi-Bhedetar road sees dismal progress in 50 months


27 March 2023  

Time taken to read : < 1 Minute


  • A
  • A
  • A

DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

PM Oli denies SPP proposal during recent visit by US official

KATHMANDU: Prime Minister KP Sharma Oli clarified that no proposal

Supreme Court orders removal of 30-year service term for Nepal Police

KATHMANDU: The Supreme Court (SC) has issued an order to

Nepal defeats Bangladesh, secures spot in SAFF U-20 Championship semi-finals

KATHMANDU: Nepal has advanced to the semi-finals of the SAFF

National Assembly passes TRC Bill

KATHMANDU: The National Assembly passed the Truth and Reconciliation Commission

Foreign Minister Dr. Arzu Rana returns to Nepal

KATHMANDU: Foreign Minister Dr. Arzu Rana Deuba returned to Nepal