Ranke-Rabi-Bhedetar road sees dismal progress in 50 months



DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

Elderly woman dies after falling from cliff

BAITADI: An elderly woman died after falling off a cliff

Silver price hits record high, crosses Rs 4,000 per tola

KATHMANDU: The price of silver reached a new record high

Senior leaders face difficulties in electronic voting at UML 11th General Convention

KATHMANDU: Senior leaders and elderly delegates have faced difficulties during

Finance Ministry tells provinces, local levels not to levy fees on goods transportation

KATHMANDU: The Ministry of Finance has told provincial and local

UML General Convention: Voting to elect new leadership begins

KATHMANDU: Voting at the 11th general convention of the CPN-UML