Ranke-Rabi-Bhedetar road sees dismal progress in 50 months



DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

Harka Sampang heads to Darchula to build bridge through voluntary labor

KATHMANDU: Chair of the Shram Sanskriti Party and House of

Both Houses of Federal Parliament meeting today

KATHMANDU: Separate meetings of the House of Representatives (HoR) and

Reminiscing Last Week: Policies, and Security Operations

KATHMANDU: Last week’s developments in Nepal reflect a moment of

New office timing begins: 9 am–5 pm workweek with two days off

KATHMANDU: From today (April 6), government offices and public bodies

Economic Digest: Nepal’s Business News in a Snap

KATHMANDU: Economic Digest offers a concise yet comprehensive overview of