Ranke-Rabi-Bhedetar road sees dismal progress in 50 months



DHARAN: The construction of Ranke-Rabi-Bhedetar road linking four districts of eastern Nepal has barely made 25 percent progress in 50 months.

The road project had to be completed some 14 months back. Still, the tasks related to track expansion, wall construction and other foundational works was continuing.

According to Chief of Federal Road Division Office, Ilam, Bidur Pokharel, only 18 percent physical progress was made on the road construction during the period of four years.

He said the contractor company made accelerated progress on road construction in the last three months.

Track expansion and wall construction were underway in the 28-km of Ranke-Rabi road section.

Likewise, the task of basement was going on for blacktopping in the Budhabare Bazaar-Bhedetar section, Division Chief Pokharel added.

Publish Date : 27 March 2023 12:19 PM

Nepal’s public debt nears Rs 2.8 trillion

KATHMANDU: Nepal’s public debt has nearly reached Rs 2.8 trillion,

Miraj Dhungana–led Gen-Z group continues protests today

KATHMANDU: The Gen-Z movement led by Miraj Dhungana is continuing

Nepal drawn in Group B for ICC Women’s T20 World Cup 2026 Global Qualifier

KATHMANDU: The match schedule for the ICC Women’s T20 World

Temporary hall being prepared for National Assembly winter session after fire damage

KATHMANDU: With the construction of the new Parliament building inside

Hetauda road expansion victims stage musical protest at Maitighar

KATHMANDU: Victims of the Hetauda road expansion project staged a