Petroleum Pipeline Project: second phase works accelerated



AMALEKHGUNJ: The second phase works under Nepal-India Cross-Border Petroleum Pipeline Project have been accelerated.

Construction of physical infrastructures including petrol tank and ‘transmix tank’ has been started at the depot located at Amalekhgunj of Bara under Nepal Oil Corporation Provincial Office.

Office Chief Pradeep Kumar Yadav said construction works have been forwarded by completing all necessary preparations.

Two petrol tanks with the capacity of 4,100 kilolitres, two transmix tanks with the capacity of 250 kilolitres, 24 automatic re-fillers, pump house and lab would be constructed under the project.

Likhita Infrastructure Pvt Ltd has got responsibility to construct all infrastructures within a year.

Nepal Oil Corporation and Indian Oil Corporation are jointly investing in the project.

Nepal Oil Corporation will invest around Rs 1.54 billion and Indian Oil Corporation around Rs 750 million in the project, added Yadav.

A target has been set to bring the project into operation from coming English New Year by completing the project within this December.

Following this, petrol would be supplied into Nepal through the pipeline. At present, only diesel is being supplied through it.

Although there is possibility to supply both petroleum products and kerosene through the same pipeline, Nepal is importing petroleum products through tankers due to a lack of space to store it.

Following the construction of the project, all petroleum products and kerosene will be supplied through the pipeline.

This would reduce technical losses and environment pollution, and save transport expenditures, said Yadav, adding that Nepal would save approximately Rs 150 million annually from it.

With this, storing capacity of the Amalekhgunj depot would increase to 24,840 kiloliters diesel and 16,630 kiloliters petrol.

The process to install two tanks with capacity of storing 5,000 petroleum products each has started in line with the government’s policy to store them for 90 days, he said.

Religare Construction Pvt. Ltd. has won the contract for the project.

Publish Date : 26 January 2023 13:15 PM

Health of Rabilaxmi Chitrakar showing improvement

KATHMANDU: The health of Rabilaxmi Chitrakar, spouse of former Prime

Minister Kulman Ghising claims completion of 101 projects in 100 days

KATHMANDU: Minister for Physical Infrastructure and Transport, Urban Development, and

Election Commission appoints officials for National Assembly polls, seven provincial offices set up

KATHMANDU: The Election Commission has established provincial offices and appointed

Around 58% of farmers registered under Farmer Registration Program

KATHMANDU: Around 58 percent of farmers across Nepal have been

Consensus on elections emerges, but Oli and Deuba want firm assurances

KATHMANDU: President Ram Chandra Paudel, Prime Minister Sushila Karki and