RASUWA: The Simbu Hydropower Centre, constructed by the Sanjen Hydropower Company, has started generating electricity.

The hydropower project which was constructed in the name of Upper Sanjen with a 14.8 MW capacity has started producing energy since August 5.

The energy produced from the hydropower project has been connected to the national transmission grid.

According to the Managing Director of Sanjen Hydropower Company, Sunil Kumar Dhungel, the construction of the Upper Sanjen Hydropower Project that had started since 2013 has now begun its production and the produced energy has been sent to the central storage through the national transmission line of the Chilime Hydropower.

Annually 88.5 million unit of energy will be generated with a total income of Rs 400 million per year, Dhungel further informed.

The power house is at an altitude of 2,180 meters from the sea level.

Publish Date : 09 August 2023 18:00 PM

34 industries face power cuts amid NEA line disputes

KATHMANDU: Kulman Ghising, Executive Director of the Nepal Electricity Authority

Kim Jong-un’s Anti-National Actions Cannot Suppress North Korean Soldiers’ Yearning for Freedom

Recently, Kim Jong-un not only proposed a “Two Hostile States

Finance Minister Poudel urges investors to invest in Nepal with confidence

WASHINGTON DC: Minister for Finance Bishnu Poudel has urged international

Cyclone Dana in Odisha: Gusty winds uproot trees, wreak havoc on communities

ODISHA: Several trees were uprooted due to gusty winds and

Finance Minister Paudel holds talks with MCC CEO in Washington DC

WASHINGTON DC: Minister for Finance Bishnu Prasad Poudel has held