Wednesday, December 17th, 2025

Tanahu hydropower project sees rapid installation of towers



TANAHU: As many as 32,000 towers have been installed for the construction of the transmission line of the 140 MW Tanahu Hydropower Project.

The towers have been installed for the construction of the transmission line under the third package of the project.

Chief of Project Engineering and Technical Division Shyamjee Bhandari shared laying the foundation for 51 towers has been so far completed.

A total of 94 towers would be installed for the construction of the transmission line.

Under package 3, KEC International, India is constructing a 36-km double circuit transmission line of 220-KV from Damauli to Bharatpur, Chitwan.

A total of 59 bighas (23 ropani, five ana) would be acquired for the construction of the transmission line.

Land within Byas municipality-13 and 14, Bandipur rural municipality-6, Anbukhaireni rural municipality-6, Devghat rural municipality-4 and 5 of Tanahun would be acquired for the same.

The Song Da Corporation, Vietnam Kalika Construction Pvt Nepal JV is constructing the 140-meter tall dam under the project phase-1.

As part of the project, two diversion tunnels are being built for the construction of main dam.

Likewise, slope cutting from both left and right side of the dam is also being done.

Breakthrough concrete lining has also gained momentum in the diversion tunnel-1 with the length of 538.5 meter and 622.5 meter long diversion tunnel-2.

Under the package-2, Shino Hydro Corporation China is carrying out works related to underground power house, main tunnel and supply, installation and operation of hydro mechanical and electro mechanical equipment.

The digging of power house has been completed and the task of concreting is continuing.

Tallrace tunnel construction is in the final stage. Installation of penstock pipe and construction of surge tank construction is underway.

Digging of 790-meter section of the 1456-meter main tunnel has been completed. Total cost of the project, including for transmission line, rural electrification and interest of the construction period is 550 million USD.

The financial management of the project was done with ADB funding of 150 million USD, JICA 184 million USD, European Investment Bank 85 million USD and Nepal government-Nepal Electricity Authority 86 million USD.

Publish Date : 08 May 2023 13:08 PM

Elderly woman dies after falling from cliff

BAITADI: An elderly woman died after falling off a cliff

Silver price hits record high, crosses Rs 4,000 per tola

KATHMANDU: The price of silver reached a new record high

Senior leaders face difficulties in electronic voting at UML 11th General Convention

KATHMANDU: Senior leaders and elderly delegates have faced difficulties during

Finance Ministry tells provinces, local levels not to levy fees on goods transportation

KATHMANDU: The Ministry of Finance has told provincial and local

UML General Convention: Voting to elect new leadership begins

KATHMANDU: Voting at the 11th general convention of the CPN-UML