35 percent physical progress achieved in Nagdhunga tunnel



KATHMANDU: The physical progress in the Nagdhunga tunnel way has reached around 35 percent while the economic progress is 43 percent.

The Nagdhunga Tunnel Way Project said 76 percent of the road construction was finished while the progress on dam is 37 percent. So far, construction of overpass is completed and flyover is under construction.

Development of two underpasses out of three is done and three box culverts are also constructed. Likewise, two out of three bridges have also completed. Till date, 1.1 km of the main tunnel is completed out of its total 2.6 km length.

The Project further shared that development of 1,384 meters of exit tunnel is finished out of total 2,557 meters. The Project has already completed the working audit as well. Similarly, 48 out of 128 meters of the cross passage is over.

The Nagdhunga Tunnel, which is the first of its kind in the country, is being developed with the concessional loan assistance from Japan International Cooperation Agency (JICA).

Publish Date : 07 April 2022 21:08 PM

Moderate rain likely in Rasuwa, Nuwakot and Dhading

KATHMANDU: Moderate rainfall is expected in Rasuwa, Nuwakot and Dhading

Press Council takes action against misleading, provocative flood content

KATHMANDU: Press Council Nepal has taken action against misleading and

LPG cylinders being filled outside Kathmandu Valley amid highway disruption

CHITWAN: Liquefied petroleum gas (LPG) bottling has begun outside Kathmandu

Iran’s Hormuz regulatory body blacklists 11 more vessels transiting through Strait over ‘non-compliance’

TEHRAN: Iran’s Persian Gulf Strait Authority (PGSA) on Wednesday (local

RSP holding Secretariat meeting to discuss current issues

KATHMANDU: The Rastriya Swatantra Party (RSP) is set to hold