35 percent physical progress achieved in Nagdhunga tunnel



KATHMANDU: The physical progress in the Nagdhunga tunnel way has reached around 35 percent while the economic progress is 43 percent.

The Nagdhunga Tunnel Way Project said 76 percent of the road construction was finished while the progress on dam is 37 percent. So far, construction of overpass is completed and flyover is under construction.

Development of two underpasses out of three is done and three box culverts are also constructed. Likewise, two out of three bridges have also completed. Till date, 1.1 km of the main tunnel is completed out of its total 2.6 km length.

The Project further shared that development of 1,384 meters of exit tunnel is finished out of total 2,557 meters. The Project has already completed the working audit as well. Similarly, 48 out of 128 meters of the cross passage is over.

The Nagdhunga Tunnel, which is the first of its kind in the country, is being developed with the concessional loan assistance from Japan International Cooperation Agency (JICA).

Publish Date : 07 April 2022 21:08 PM

Gold price down Rs 10,100 per tola

KATHMANDU: Gold and silver prices declined on Wednesday compared to

Shekhar Koirala secretariat denies receiving any seven-point proposal from party establishment

KATHMANDU: The secretariat of Nepali Congress leader Shekhar Koirala has

Finance Minister says vested groups targeting PM, himself over probe

KATHMANDU: Finance Minister Swarnim Wagle has alleged that both the

Drug abuse, security concerns plague holding centre housing Thapathali evictees

KATHMANDU: Families displaced from the Bagmati riverbank in Thapathali and

Finance Minister Wagle alleges smear campaign amid budget debate

KATHMANDU: Finance Minister Swarnim Wagle has accused certain groups of