35 percent physical progress achieved in Nagdhunga tunnel



KATHMANDU: The physical progress in the Nagdhunga tunnel way has reached around 35 percent while the economic progress is 43 percent.

The Nagdhunga Tunnel Way Project said 76 percent of the road construction was finished while the progress on dam is 37 percent. So far, construction of overpass is completed and flyover is under construction.

Development of two underpasses out of three is done and three box culverts are also constructed. Likewise, two out of three bridges have also completed. Till date, 1.1 km of the main tunnel is completed out of its total 2.6 km length.

The Project further shared that development of 1,384 meters of exit tunnel is finished out of total 2,557 meters. The Project has already completed the working audit as well. Similarly, 48 out of 128 meters of the cross passage is over.

The Nagdhunga Tunnel, which is the first of its kind in the country, is being developed with the concessional loan assistance from Japan International Cooperation Agency (JICA).

Publish Date : 07 April 2022 21:08 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

PM Balen Shah tells newly commissioned army officers to serve with discipline

KATHMANDU: Prime Minister Balendra Shah has urged newly commissioned officers

Two killed, six injured in jeep accident in Kanchanpur

KANCHANPUR: Two people died on the spot and six others

Tourism entrepreneurs optimistic as two-day weekend aims to boost domestic travel

CHITWAN: Local tourism stakeholders have expressed high hopes that the

Bharaul Gold Cup: Chitlang Football Club advances to semi-finals

SUNSARI: Chitlang Football Club has secured a place in the