Sailung Construction vows to complete Nagarkot road expansion by coming March-end



BHAKTAPUR: The Kamalbinayak Nagarkot Road Construction Project and Sailung Construction Pvt Ltd have pledged to complete the construction of the much-awaited Bhaktapur-Nagarkot road by mid-March next year.

At an interaction program organized by Changunarayan municipality on Wednesday to mount pressure for an expedition of road construction, project chief Gautam Shrestha vowed to complete the works by mid-March.

It may be noted that the timeline for the construction and expansion of the Bhaktapur-Nagarkot road section has been extended for the seventh time.

On the occasion, Madhav Khadka of Sailung Construction admitted serious managerial errors on part of the contractor company in the road construction and pledged to complete the stipulated works soon.

Publish Date : 23 December 2021 15:00 PM

Today’s News in a Nutshell

KATHMANDU: Khabarhub brings you a glimpse of major developments of

Security Printing Centre begins printing long-pending driving licenses

KATHMANDU: The Security Printing Centre has started printing driving licenses

Tiger census completed in Shuklaphanta

KANCHANPUR: The tiger census in Shuklaphanta National Park has been

Court orders release of UML MP Rekha Sharma

KATHMANDU: CPN-UML lawmaker Rekha Sharma, a member of the Lumbini

NC calls parliamentary party meeting for Monday

KATHMANDU: The Nepali Congress (NC) has called a meeting of