Dordi-1 hydro project construction at final stage



LAMJUNG: The construction of Dordi-1 hydropower project underway in Lamjung district has reached a final stage.

The construction, which should have been accomplished earlier, had been delayed after the floods in the Dordi River incurred damages to the wall of the sand-trap and the stilling basin on June 15.

According to Project Manager Ujwal Silwal, the civil construction of the canal wall has been completed while that of the power house is at the final stage.

Similarly, the installation of electromechanical equipment has reached the final stage.

The construction work of the project will be completed by mid-January next year and start generating electricity, said Silwal.
The hydro project had started in 2074 BS.

Publish Date : 10 November 2021 13:32 PM

ICC T20: Nepal set 134-run target for West Indies

KATHMANDU: With a fighting half-century from Dipendra Singh Airee, Nepal

Farmers of Tanahun earn crores from orange sales

DAMAULI: Farmers in Tanahun district have earned crores of rupees

Nepali Army marks 263rd foundation day on Mahashivaratri

KATHMANDU: Nepal’s premier security force, the Nepali Army, celebrated its

Birgunj Customs collects Rs 135 billion in seven months

BIRGUNJ: The Birgunj Customs Office has collected Rs 135.48 billion

Mustang sends 4,391 kg of waste for recycling in six months

MUSTANG: A total of 4,391 kilograms of solid waste has